Page 156 - Estimators Piping Man Hour Manual
P. 156

Section Two-FIELD FABRICATION     139

             SCHEDULE          3O  OB    4O   RUBBER       LINED
                    STEEL      PIPE     AND    FITTINGS


                           MAN  HOURS PER  UNITS LISTED
          Size           Pipe       Cut  & Thread   Make-On s     Bolt-Ups
          Ins.        Per  L.  F.      Each          Each           Each
          1-1/4          .22           .15            .30            .60
          1-1/2          .23           .16            .35            ,65

          2              .25           .25            ,40            .70
          2-1/2          .27           .30            .45            ,80
          3              .30           .32            .50            ,85
          3-1/2          .33           .35            .55           LOO

          4              .35           .50            .60           1.20
          5              .38            --             --           1.30
          6              .40            --             -            1.50
          8              .52            --             ..           2.10
          10             .60            --             -            2.70

          12             .75            --             ..           3.40

     Pipe Units:  Pipe units  include  rigging, erecting  and aligning of pipe.
     Cut  Thread  Units:  Cut  and  thread  units  include  hand  cutting  and  threading  of  pipe two
         inches  and  smaller  and  machine  cutting  and  threading  of  size  two  and  one half
         inches  and larger.
     Make-On  Units:  Make-on  units  include  making  on  of  screwed  type  fittings.  Ells  = two
        raake-ons, tees = three make-ons,  etc.

     Bolt-Up  Units:  Bolt-up units  include bolting together  of flanged  connections.
     All  Units:  All units  include unloading, handling  and hauling to  storage  and  erection  site.
     If  pipe  is  received  from  factory  in  flanged 20  foot  lengths  add  10 percent  to pipe handling
     manhours  for handling of additional weight.

     Man  hours do not  include  supports or scaffolding. See  respective  tables  for these  charges.
   151   152   153   154   155   156   157   158   159   160   161