136   Section Two-FIELD FABRICATION

                INSTRUMENT          AND    CONTROL        PIPING


                                     TRACING

      Man hours  are  for all  fabrication and installation or erection  of all  copper  tubing,  steel piping,
      alloy  tubing  and capillary  tubing  used  for  tracing  or  for interconnecting all  instruments and
      control  devices, regardless of location,  whether on panel  board, piping or  equipment, for  all  in-
      strument  and control  piping  up to  and including one  (1) inch.

      Man  hours  include  the  labor  of  installing  all  connections,  fittings,  and  supporting  clips  or
      hangers.


      Should  the  lines  be group installed and protected by casings or channels,  the installation  labor
      of  such casings or  channels are  extra.




      Runs up to  10 feet                            5.0 Man hours  total
      Runs over  10 feet                             0.4  Man hours per  foot  of  length
      Asbestos wrap pipe before tracing              0.05 Man hours per  foot


               SOLDERED         NON-FERROUS            FITTINGS

                                  NET MAN HOURS EACH

       Nominal   Coup-                       Re-                 Caps 8s
       Size— Ins.  lings  Ells  Tees  Flanges ducers Adapters Unions  Plugs  Valves

        1/8-3/8   ,16    .17    .24    .16    .18    .15    .18    .08    .35
        1/2       .22    .23    .33    .22    .25    .20    .25    .11    .40
        3/4       .28    .29    .42    .28    .32    .25    .35    .14    .45
        1"        .43    .44    .63    .32    .50    .40    .55    .22    .60
        1-1/4     .80    .85   1.20    .64    .85    .75    .90    .40   1.00
        1-1/2     .85    .90   1.26    .70    .90    .80   1.00    .42   1.15

        2         .96   1.00   1.44    .90   1.00    .92   1.15    .50   1.25
        2-1/2    1.50   1.55   2.25   1.15   1.65   1.35   1.85    .75   2.10
        3        1.95   2.00   2.91   1.40   2.00   1.80   2.25    .95   2.50
        4        2.00   2.25   3.00   1.65   2.15   1.90   2.75   1.00   3.00

      Man  hours  include  procuring,  handling,  and  complete jointing  or  making  on  of  solder-type
      cast  and wrought  pressure  type  brass or copper  fittings.
      Man hours  do not  include  installation  of  tubing or pipe,  supports,  instruments  or  scaffold-
      ing.  See respective  tables  for these charges.