TABLE 1.4 Council of American Structural Engineers Submittal Review Checklist
Project: Project Manager: Reviewer:
Project No.: Engineer: Date:
Item Yes No N/A Comment
I. General
A. Is general contractor’s review stamp
present and signed on all sheets?
B. Have all sheets been entered into
submittal log?
C. Have all sheets been reviewed for
general completeness immediately
upon receipt?
D. Have dimensions given on struc-
tural drawings been verified on
submittals?
E. Have any unusual or questionable
conditions been reviewed by a
senior engineer?
F. Have all submittals required by
contract documents been provided?
G. Do general notes on shop drawings
agree with structural drawings and
specifications?
H. Have submittals been
reviewed/returned within firm’s
general policy time period?
II. Concrete Formwork (if Required)
A. Has dimensional layout of elements
been reviewed?
B. Have shoring/reshoring require-
ments been submitted for informa-
tion purposes?
III. Mild Reinforcing
A. Have size, quantity, spacing, and
layout been reviewed?
B. Has steel grade(s) been reviewed?
C. Have lap lengths, stagger, and loca-
tions been reviewed?
D. Have reinforcing lengths been spot-
checked?
1.52