TABLE 1.4 Council of American Structural Engineers Submittal Review Checklist (Continued)
Project: Project Manager: Reviewer:
Project No.: Engineer: Date:
Item Yes No N/A Comment
E. Have configurations (hooks, offset
bends, ties, stirrups) been reviewed?
F. Have chair heights and cover been
reviewed?
G. Have shop drawing details been
confirmed with appropriate (struc-
tural/architectural) drawing details?
H. Have epoxy coatings and galvaniz-
ing requirements been confirmed
for reinforcement and accessories?
IV. Posttensioning
A. Have loss calculations been
reviewed prior to shop drawing
review?
B. Has tendon layout been confirmed
based on actual tendon forces?
C. Is tendon-stressing sequence
appropriate?
D. Are certified mill reports provided?
E. Has construction joint layout been
reviewed?
F. Are all tendons accessible for
stressing?
G. Are tendon profiles and chair
heights correct?
H. Have chair heights and cover been
reviewed?
I. Have shop drawing details been
confirmed with all structural
drawing details?
J. Have epoxy coatings and galvaniz-
ing requirements been confirmed
for reinforcement and accessories?
K. Are placing sequences appropriate?
V. Precast Concrete
A. Are all loadings correct?