              2.114 Initial volume required to achieve a volume with hematite

              Input(s)
                 W 1 :  Initial Mud wt. (ppg)
                 W 2 :  Required mud wt. (ppg)
                 V f :  Final Volume (ppg)

              Output(s)

                 V i :  Starting Volume (bbl)

              Formula(s)

                                                               40 W  2
                                                       V ¼ V
                                                         i   f
                                                               40 W
                                                                     1
              Reference: Formulas and Calculations for Drilling, Production and Workover, Second Edition, Lapeyrouse, Page: 84.

              2.115 Injection/casing pressure required to open valve

              Input(s)
                 P bt :  Bellows or Dome Pressure at Valve Depth (psi)
                 P 2 :  Production or Tubing Pressure at Valve Depth (psi)
                                               2
                 A p :  Area of Valve Port or Seat (in. )
                                       2
                 A b :  Area of Bellows (in. )

              Output(s)
                 P1:  Injection/Casing Pressure Existing at the Valve Depth (psi)


              Formula(s)


                                                                   A p
                                                         P   P
                                                          bt    2
                                                                   A b
                                                    P1 ¼
                                                                 A
                                                                  p
                                                            1
                                                                 A
                                                                  b
              Reference: Beggs, H. D. 2003. Production Optimization using Nodal Analysis, OGCI and Petroskills Publications, Second
              Edition, Chapter 5, Page: 166.
              2.116 Input power of a pump—Using fuel consumption rate
              Input(s)

                 Q f :  Rate of Fuel Consumption (lbm/h)
                 H:   Fuel Heating Value (BTU/lb)


              Output(s)

                 P i :  Input Power (hp)
   126   127   128   129   130   131   132   133   134   135   136