Page 432 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 432

Lube, Seal and Control Oil System Best Practices  Best Practice 7 .16
              components as they will operate in the field. In order to ensure  testing both together. Additional costs of such a test should be
              a valid factory test, a test agenda should be prepared approxi-  evaluated against the potential reduction of reliability and loss of
              mately two months before test date and reviewed by the  operation time in the field if any malfunctions exist that were
              equipment purchaser. A typical test agenda outline is included  not determined by test of the console alone.
              at the end of this section. In addition, a typical auxiliary system
              test agenda is included courtesy of G.J. Oliver, Inc. The test  Functional lube/seal system test
              agenda should endeavor to confirm the functional operation of
              every component in the system. Specific areas of concern are  procedure outline
              discussed below.
                                                                    Objective:  To confirm proper functional operation of the entire
                                                                               system prior to equipment start-up
              Flushing
                                                                    Procedure  Detail each test requirement. Specifically note
              Component system flushing is required as an inspection point  format:  required functions/set points of each component.
              and should be accepted prior to the initiation of the test.      Record actual functions/set points and all
              Additionally, all test agendas should be structured such that    modifications made.
                                                                    Note:      All testing to be performed without the unit in
              a limit for each item to be tested is specifically defined. The    operation.
              flushing acceptance criteria must be mutually agreed upon
              and be adhered to during the review of flushing the
              operation. Refer to a typical field flushing procedure in B.P.
              7.18.                                                I. Preparation
                                                                   A. Confirm proper oil type and reservoir level.
              Confirm arrangement details                           B. Confirm system flush is approved and all flushing screens are
              Prior to the commencement of the test, make sure that the  removed.
              arrangement of all components, controls and instruments agrees  C. Confirm all system utilities are operational (air, water,
              with the design requirements. Any discrepancies should be  steam, electrical).
              corrected prior to functional test.                  D. Any required temporary nitrogen supplies should be
                Confirm proper test fluid and capacity are present to prior to  connected.
              initiation of the test.                              E. All instrumentation must be calibrated and control valves
                                                                      properly set.
              Temporary test setup                                 F. Entire system must be properly vented.
              If it is necessary to import utilities or switches for the test that  II. Test procedure
              are not normally present, as in the case of steam turbine steam
              generator and control switches, these items must be confirmed  A. Oil reservoir
              prior to test initiation. In addition, a means of confirming proper  1. Confirm proper heater operation.
              flow rates, temperature and pressure during the test must be  2. Check reservoir level switch and any other components
              provided. Supply lines to the unit must be provided with  (TIs, vent, blowers, etc.).
              properly size orifices to duplicate unit flow requirements.  B. Main pump unit
                                                                     1. Acceptable pump and driver vibration
              Functional testing                                     2. Absence of cavitation
                                                                     3. Pump and driver acceptable bearing temperature
              Having confirmed proper test setup, calibration of all in-
              strumentation, proper fluid and test instrumentation, the  4. Driver governor and safety checks (uncoupled) if driver is
                                                                        a steam turbine
              functional test is now ready to be performed. As a minimum the
              following tests should be performed on any auxiliary system  C. Auxiliary lube pump unit: same procedure as item B
                                                                      above.
              console:
                                                                   D. Relief valve set point and non-chatter check.
              - Relief valve test (if supplied)                    E. Operate main pump unit and confirm all pressures,
              - Transfer valve test                                   differential pressures, temperatures and flows are as
              - Auto start test of auxiliary pump with the following  specified on the system schematic and/or bill of material.
                 conditions:                                       F. Confirm proper accumulator pre-charge (if applicable).
              - Main pump tripped                                  G. Confirm proper set point annunciation and/or action of all
              - Two pump operation (main pump in operation, standby   pressure, differential pressure and temperature switches.
                 pump started)                                     H. Switch transfer valves from bank ‘A’ to bank ‘B’ and confirm
                                                                      pressure fluctuation does not actuate any switches.
                During all functional testing, any system pulsations or pres-  I. Trip main pump and confirm auxiliary pump starts without
              sure drops above specified values are reason for non-acceptance  actuation of any trip valves or valve instability.
              of test. All components not meeting requirements must be
                                                                     Note: Pressure spike should be a minimum of 30% above any
              corrected and units must be completely retested.     trip settings
                The value of testing the auxiliary console with the unit should
              be seriously considered. Since the console and the unit piping  J. Repeat Step I above but slowly reduce main pump speed (if
              from the specific auxiliary system, there is a significant benefitto  steam turbine) and confirm proper operation.

                                                                                                               403