Page 555 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 555

Be st Practice 1 0.1          The Post-Shipment Phase: Installation, Pre-Commissioning, Commissioning and Start-up Best Practices


         Best
         Best Practice 10.1Practice 10.1
         Review and finalize machinery installation details well in  effective planning, management and implementation
         advance of site construction activities to ensure optimum  during the project construction phase.
         safety and reliability for the plant life cycle.     The following examples show how the reliability of properly speci-
           The relevant areas to concentrate on are as follows:  fied, designed and tested machinery was challenged by inadequate
           Prepare, review and approve all site installation procedures (See  construction phase execution:
           ‘Supporting Material’ below for specific procedures).    Preservation procedures not prepared in advance, general in nature
           Confirm spare part orders, delivery dates, storage facilities and  and not implemented
           preservation compounds.                            Instruction manuals not on site when required and when received,
           Review and approve all machinery instruction manuals prior to  not complete
           shipment, and require manuals be shipped at the same time as the    Spare parts not on site when required resulting in start-up delays
           machinery.                                         Special tools missing and not available resulting in start-up delays
           Review the special tool list during the engineering phase and require
           their shipment at the same time as the machinery.
           Establish a ‘material receipt’ procedure to confirm that all required  Benchmarks
           material has been received on or before the promised date.  This best practice has been used since the mid-1980s for large pet-
                                                            rochemical projects, and requires that all machinery construction de-
           Confirm that there is full coordination between the engineering/  tails be addressed during the engineering phase of the project. This
         procurement (EP) and construction (C) groups to ensure the above  best practice has resulted in smooth, timely start-ups for large ma-
         best practice guidelines are executed well before the construction  chinery, and critical machinery reliabilities of maximum safety and re-
         phase.                                             liability (greater than 99.7%).

         Lessons Learned
         Critical machinery safety and reliability is not ensured only
         by proper specification, design and testing but depends on





       B.P. 10.1. Supporting Material                       Site procedures
                                                            The importance of site installation procedures cannot be over-
       Regardless of the quality of design and manufacture; regard-  emphasized. Figure 10.1.2 shows the most commonly required
       less of a successful test and efficient shipment; installation  site installation procedures.
       will determine the amount of maintenance required and the  It must be remembered that the objectives of the construc-
       resulting revenue of the process unit. Figure 10.1.1 shows the  tion contractor and of the end user are identical in terms of
       general site considerations that are required for a successful  profit. However, they are dissimilar in the means used to achieve
       field installation. Each one of these items will now be  these common objectives. The contractor’s objective is to con-
       covered.                                             struct a safe and reliable process unit within the budget and on
                                                            time. This objective is opposed to the end user’s objective,
                                                            which is to operate the process unit for thirty years or more at
                                                            maximum profit and thus requires maximum reliability of the
                                                            installed equipment. The only leverage that the end user has in
                                                            meeting his objectives is to require practical, proven site
                                                            installation procedures that will result in the most reliable, safe
                                                            and cost effective installation of his equipment. Frequently the
                                                            contactor will rely on the equipment vendor to provide most of
                                                            the site procedures. It is strongly recommended that the end
                                                            user, early in the project, require approved procedures for every
                                                            major site installation milestone. These procedures include, but
                                                            are not limited to:
                                                            - Equipment preservation
                                                            - Equipment installation
                                                            - Grouting
                                                            - Alignment
                                                            - Flushing
                                                            - Functional checks
                                                            - Initial run in of equipment

                                                              It must be mentioned that preservation procedures are often
       Fig 10.1.1   General site considerations             ignored early in a construction project and become written and

           526
   550   551   552   553   554   555   556   557   558   559   560