Page 556 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
        P. 556
     The Post-Shipment Phase: Installation, Pre-Commissioning, Commissioning and Start-up Best Practices  Best Practice 1 0.1
              Fig 10.1.2   Site installation procedures
              implemented too late to effectively prevent equipment de-  required. Many of the tools, such as hydraulic jacks, special
              terioration due to corrosion. Again, require procedures be  mounting devices, etc. also will require preservation during
              written and approved well in advance in the start of  storage to prevent corrosion. Many times this requirement is
              construction.                                        overlooked. Be aware!
                Aspecific ‘initial run in procedure’ for each major piece of  An example of not properly storing special tools and spare
              rotating equipment should be reviewed by the end user well  parts is a high humidity, tropical island installation where
              in advance. It is recommended that the end user review these  the spare rotor and coupling hydraulic mounting tools were to
              procedures during the shop test with vendor field service  be used for a turnaround. They were not inspected prior to the
              engineers to ensure that the run in procedure is in accordance  turnaround and the result was that the spare rotor could not
              with vendor and plant best practices. An example of not  be installed due to excessive corrosion. The coupling hydraulic
              performing a pre-run in review and the consequences of not  mounting adapter had to be replaced with a new adapter due to
              doing this concerned a large, high-pressure, condensing, steam  excessive corrosion. It should be noted that this equipment was
              turbine cold start-up time vs. speed curve. Since the turbine  stored in a sealed container with a nitrogen purge but un-
              was designed for an automated sequenced start, the cold  fortunately the seal was faulty and the nitrogen purge pressure
              start-up curve was programmed into the PLC without de-  was not monitored.
              tailed review by the end user. The curve was simulated and
              did not take the specific parameters of the application into  Installation manuals
              account. The result was a severe rub that damaged rotor and  Like site procedures, installation manuals frequently arrive after
              stationary internals, and resulted in over a 40 day plant start-  they are first required. The installation manual will contain
              up delay. The daily profit of this plant was approximately  valuable information pertaining to receipt of equipment, pres-
              0.25 $MM.
                                                                   ervation, interim storage and of course, installation. It is
                                                                   recommended that the end user again require that manuals be
              Construction special tools
                                                                   approved and received well in advance of the start of any in-
              Most of the equipment that is installed will be custom designed.  stallation activity.
              Therefore, special tools will be shipped with the equipment that  In an effort to ensure that the instruction manual contains
              can only be used for that particular item. Consequently, these  information that is accurate and specific to the job, we have
              tools must be listed and stored in a proper location that will  writteninto the jobspecification that the instruction book
              allow maintenance personnel to easily locate them when  shall be completely reviewed at the time of the shop test and
                                                                                                               527





