Page 561 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 561

Be st Practice 1 0.6          The Post-Shipment Phase: Installation, Pre-Commissioning, Commissioning and Start-up Best Practices
       bolts and chocks should be greased for ease of operation once
       the grout starts to cure.                              1. In accordance with grout manufacturers’ procedures
                                                              2. Wax or grease all forms
       Epoxy grout                                            3. Limit thickness of pour to 10 cm (4")
                                                              4. Fill bolt sleeves or pockets
       Epoxy grout is clearly the grout of choice for critical (un-spared)  5. Check for voids. Fill with epoxy pressure grout
       equipment installation, since it lasts the longest and is imper-  6. Seal grout holes
       vious to most external sources. Figure 10.5.2 presents some
       epoxy grout considerations.
          It is important that epoxy grout be poured in accordance with  Fig 10.5.2   Epoxy grout considerations
       the grout manufacturer’s recommendations. Most contractors  Non-shrink or cementous grout
       need experience in epoxy grout installation. In fact, it has been
       our experience that an on-site demonstration of epoxy grout by  Frequently for cost considerations, contractors will attempt to
       the epoxy grout manufacturer is a worthwhile expenditure, and  use non-shrink or cementous grout on large pieces of equip-
       saves countless repours and project delays. Some other epoxy  ment. In certain instances this is acceptable, as in the case of
       grout considerations are:                            large oil console foundations, which are usually installed with
                                                            cementous grout for reasons of mass. This action solidifies the
       - Wax or grease all forms                            console base and minimizes pipe and component vibration.
       - Limit thickness of pour to approximately 10 cm (4 in)  It should be mentioned that some types of non shrink grout
       - Ensure that proper mixing and pouring tools are available  incorporate metal filings. It has been found in some instances
       - Fill bolt sleeves or pockets to ensure that grout does not spill  that these filings will corrode with time, and cause separation of
          into these areas                                  grout from the foundation. Prior to application of any grout,
       - Check for voids and fill with epoxy pressure grout when  a proper procedure and details of the grout must be defined. In
          required                                          the event of any doubts ask the original equipment manufac-
       - Seal grout holes in metal base plates              turer regarding his considerations.








         Best Practice 10.6Practice 10.6Practice 10.6Practice 10.6
         Best
         Best
         Best
         Require that the following best practices be executed to  The above action will produce on-schedule start-ups and optimum
         ensure proper process piping to machinery flange align-  reliability for the life of the machinery.
         ment and foundation continuous support (soft foot):
                                                            Lessons Learned
           With process piping disconnected, confirm that the baseplate does
           not rise more than 0.05 mm (0.002 in) when the foundation bolts  Improper process piping attachment and foundation pro-
           adjacent to a dial indicator are loosened.       cedures cause prolonged machinery component (bear-
           Process piping is floated (not connected) to the machinery flanges  ings, seals and internal rub) problems that have resulted in
           resulting in a maximum mating to machinery flange parallel  low component MTBFs (less that 12 months).
           difference of 0.25 mm (0.010 in) at four locations 90 degrees apart.
           All flange bolts can be installed without any external forces applied  Benchmarks
           to the process piping.
                                                            This best practice has been used since the mid-1980s to result in
           When the process piping is connected to the machinery, two dial
                                                            optimum installed machinery component MTBFs (> 100 months).
           indicators reading shaft or coupling hub movement, mounted at 90
           degrees, do not register movement greater than 0.05 mm (0.002 in).
           Note: Dial indicators must be mounted off of the machine (on the
           coupling guard or an independent support).



       B.P. 10.6. Supporting Material                       ‘bad actors’. They both are relatively easy to prove; however,
                                                            they can be very difficult to correct. The purpose of this section
       Have you ever been called into your supervisor’soffice and ques-  is to present the reasons why excessive pipe stress and soft foot
       tioned on how to properly install the equipment or a component?  cause bad actors, how to prove these problems exist and the
       Have you ever had the experience of installing a component  most cost-effective method to correct them.
       (bearing) only to have it fail repeatedly over the following months  Before we can understand how pipe stress and soft foot can
       and became a ‘bad actor’? What is the problem? Is it your assembly  cause equipment component failures, we must know what pipe
       procedures, the installation, the equipment or the process?  stress and soft foot are! Figure 10.6.1 presents these facts.
          The subject of this section is equipment pipe stress and soft  Naturally, all equipment cases are designed to accommodate
       foot. Without a doubt, these factors are prime contributors to  reasonable pipe loads and minimal load due to soft foot.

           532
   556   557   558   559   560   561   562   563   564   565   566