Be st Practice 1 0.4          The Post-Shipment Phase: Installation, Pre-Commissioning, Commissioning and Start-up Best Practices
                                                            crankcase and crossheads. After the foundation was set, with
                                                            the foundation bolts in place, it was discovered that the bolt
                                                            locations had moved from the original positions, and that the
                                                            crankcase could not be positioned over the foundation bolts.
                                                            The re-bar had interfered with the foundation bolts causing
                                                            them not to be correctly positioned. The result was complete
                                                            foundation rework to correctly position the foundation bolts
                                                            that resulted in a delay of one month to the construction
                                                            schedule. At that time the lost revenue was approximately
                                                            $1 MM per day.
                                                              One last word regarding foundation bolts. It is easy to mis-
                                                            locate the bolt locations relative to the machinery base plate
                                                            holes. Before bolt holes are randomly elongated to facilitate
                                                            misplaced location bolts, all facts should be discussed with both
       Fig 10.4.1   Foundations                             the contractor and the vendor of the equipment. Irresponsible
                                                            action regarding elongation of bolt holes has caused machinery
       provided. It is wise to epoxy-grout sole plates to facilitate easy  problems. Fabricated foundation bolts on which welding is
       removal and installation of equipment during maintenance. Sole  used in the fabricated assembly must be stress relieved after
       plates must be level in themselves and all other planes.
                                                            welding.
       Foundation bolts
                                                            Leveling
       Each equipment manufacturer has foundation bolt re-
       quirements. It is a good idea to review the contractor’s foun-  Figure 10.4.3 presents the basics of leveling of equipment.
       dation bolt arrangements prior to any equipment installation and  Equipment must be leveled within a tolerance of 0.05 mm
       ensure that the contractor’s procedure, types of bolts and bolt  per meter and confirmed with a calibrated engineer’s level. Any
       arrangement, meet or exceed the equipment vendor’s re-  special leveling instructions given by the vendor must be
       quirements. Many a project has been delayed by not in-  followed. In the case of reciprocating equipment, it is important
       corporating this requirement. Figure 10.4.2 shows three typical  that shims straddle hold down bolts. When jacking screws are
       installation arrangements for anchor bolt installations.  used for leveling equipment it is not necessary to remove them
          A case history for the installation of a large reciprocating  after grouting, but they must be backed off at least two turns
       compressor in a refinery shows how poor planning can cause  and the hold down bolts must be retorqued to their correct
       significant construction delays. The foundation re-bar pattern  value after grout has adequately cured. There should be a min-
       was not coordinated with the foundation bolt pattern for the  imum of one jacking bolt for each hold down bolt.




                                                                                 Fig 10.4.2   Anchor bolt installations
                                                                                 (Courtesy of ME Crane, Consultant)