The Post-Shipment Phase: Installation, Pre-Commissioning, Commissioning and Start-up Best Practices  Be st Practice 1 0.10


               Best Practice 10.10Practice 10.10Practice 10.10
               Best
               Best
               Perform driver solo runs to confirm that all the phases of  Lessons Learned
               construction have been completed successfully, and that  Failure to completely check out driver operation prior to
               the control and protection systems operate properly.  plant start-up will result in start-up delays and expose the
                  These runs will also confirm:                     plant to lower machine reliability until the first scheduled
                 Proper functional operation of all auxiliaries    turnaround.
                 Overspeed protection system check                   In the rush to complete commissioning activities and start plant
                                       )
                 Accumulator precharge check                       production, pre-start-up checks are often minimized. Any critical (un-
                                         )
                 Trip valve manual exercise check                  spared) machinery reliability issues that are not identified prior to plant
                 Governor system check                             operation will expose the plant to corresponding safety, reliability and
               )
                 ¼ where applicable                                revenue losses until they can be corrected (usually during the first plant
                                                                   turnaround four or five years after start-up).
                  In addition to ensuring proper operation of the driver and associated
               auxiliary systems, the solo runs are an excellent training opportunity for
               site personnel.                                     Benchmarks
                  Awareness of the function and design basis of the various com-  This best practice has been used since 1984 to identify and correct
               ponents of the driver and support systems by site personnel will result  critical machinery driver potential safety and reliability issues prior to
               in a greater understanding of condition monitoring requirements and  plant start-up to optimize critical machinery train reliability (> 99.7%).
               increase driver safety and reliability.



              B.P. 10.10. Supporting Material                             Failure of ‘final driver’ (internal governor component)
                                                                          Zero speed inputs
                                                                      - Confirm manual transfer to and from backup governor
              Electro-hydraulic governor functional test                and ‘emergency override’
              procedure outline                                       - Check raise and lower speed controls while in backup
                                                                        governor mode
               Objective:  To confirm proper system functional operation prior  - Confirm governor shutdown (trip) operation under the
                           to equipment start-up.                       following conditions:
               Procedure   Detail each test requirement. Specifically note    Overspeed setting
               Format:     required functions/set points. Record actual    Failure of both main and backup governor controls
                           functions/set points and all modifications made.
                                                                   III Corrective action
                           Note: All testing to be performed without the unit in  - Failure to meet any requirement in Section II requires
                           operation
                                                                        corrective action and retest
                                                                      - Specifically note corrective action
               I Preparation                                          - Sign off procedure as acceptable to operate
                 - Confirm all shut down contracts are in the normal
                   condition
                 - Confirm all power supplies are on                Steam turbine solo run functional test
                 - Secure necessary test equipment:
                     Pressure sources (nitrogen bottles) for pressure  procedure outline
                      simulation at transmitters
                     Frequency generators for simulating speed signals  Objective:  To confirm acceptable mechanical operation of the
               II Test procedure                                               steam turbine, governor system and safety (trip)
                 - Take required action to put system in ‘run’ mode            system
                 - Open trip and throttle valve only after insuring the main  Procedure  Detail each test requirement. Specifically note
                                                                               required test limits (Note: shop test data should be
                                                                    Format:
                   steam block valve is closed                                 used to define acceptable limits). Record actual test
                 - Simulate turbine start, slow roll and any start sequence    values using appropriate instrumentation and note all
                   ‘hold’ points up to minimum governor operating point        modifications made.
                 - Confirm proper operation of ‘raise’ and ‘lower’ speed
                   buttons                                         I Preparation
                 - Connect external process signal inputs (one at a time)  - Confirm all auxiliary system tests are complete
                   and confirm proper governor action to input signal    (governor, lube system, etc.)
                   variation                                          - Confirm all inlet steam lines have been cleaned and
                 - Check overspeed override feature                     signed off
                 - Confirm automatic transfer to and from backup governor  - Confirm all installed instrumentation is calibrated
                   ‘position control’ for each of the following cases:  - Secure all required instruments:
                     Loss of main governor power supply                   Calibrated pressure and temperature gauges
                     Zero external input signal                           Oscilloscope(s)