Page 253 - Global Project Management Handbook
P. 253

12-14           COMPETENCY FACTORS IN PROJECT MANAGEMENT

        Strategic Cities Program
        In the late summer and early fall of 2004, the insurgency was increasing, particularly
        in the Sunni triangle area of central Iraq. The MNFs, the U.S. Department of State,
        and the Iraqi government directed a focused effort to win the peace in these cities. The
        Strategic Cities Program (SCP) was created to accomplish this. The program plan was
        simple; first, the MNFs would defeat the insurgency, and then, immediately following
        the end of hostilities, various groups, including the PCO, would move in to start
        rebuilding the city, and the IRMO would coordinate the stabilization process.


        Program Contractor Role Adjusted
        As mentioned earlier, a contractor called the Program and Contracting Office Contractor
        (PCOC) was retained on a cost-plus basis to manage the IRRF II program. This created
        a situation where one government contractor was managing other government contrac-
        tors. In the summer of 2004, it became clear that this arrangement would not work for
        two reasons. First, the contractor was slow to mobilize the right people to Iraq, and sec-
        ond, the government moved strong leaders into Iraq early on. With the PCOC short of
        the right people to manage the program, government leaders stepped in to run the pro-
        gram. This illustrated one advantage to cost-plus contracts. That is, when something is
        not working, you can quickly adjust a contractor’s scope to correct the situation.


        A DB Contractor Fails

        A total of 13 cost-plus contracts were awarded to DB contractors. All the contractors
        mobilized to Iraq in the second quarter of 2004 and began work immediately. All but
        one contractor was able to subcontract work to local Iraqi subcontractors and make
        positive progress on projects.
           It became apparent in late summer of 2004 that this one contractor was not going
        to do any actual on-site project work. At that time, the PCO had two options. One
        option was to fire the contractor and potentially sue the contractor for not fulfilling the
        contract, and the second option was to negotiate a “termination for convenience.” In

        the end, the PCO negotiated a termination for convenience with the contractor because
        it was the quickest thing to do, and the entire focus of the program was speed, that is,
        to get projects started. It was later reported in the press that the contractor left Iraq
        because it was unsafe to work in Iraq, but the press missed the fact that all the other
        12 contractors were still working in Iraq.


        Contracting Office
        Regulatory compliance is a big deal when awarding and executing government con-
        tracts. And if the contracts are cost-plus, which all the contracts in Iraq were, the
        bureaucratic regulatory compliance effort becomes a bigger effort. Because of this, the
        government contracting officers and the contracting office were very important. In
        fact, it was not unusual that the contracting officer thought that he or she was the proj-
        ect manager because he or she was responsible for making sure that funds were only
        disbursed for work that was completed in compliance with the contract and within the
        intent of the law.
   248   249   250   251   252   253   254   255   256   257   258