Page 250 - Global Project Management Handbook
P. 250

LESSONS LEARNED: REBUILDING IRAQ IN 2004   12-11

        infrastructure. It was not uncommon to find pumping stations that had not had annual
        maintenance in a decade.
           The collective impacts of lack of maintenance for several decades, the war, and
        looting created a dilapidated infrastructure with many needs. In fact, the looting was
        worse than anticipated, which caused many rehabilitation projects to become rebuilds.
           Only 40 percent of the nation had access to potable water, and 90 percent of the sew-
        erage went untreated. The lack of potable water was the main cause of the infant and
        child mortality rate exceeding 10 percent. Further, the Sweet Water Canal that moved
        water to the city of Basrah on the southern tip of Iraq failed on occasion, leaving the more
        than 1 million residents of Basrah without water for a period of five or six days. And 1
        million people without water on a 120ºF summer day become somewhat hostile.
           Five million of Iraq’s 25 million citizens were without electricity. And the 20 million
        who did have access to electricity would experience rolling blackouts, with electricity typi-
        cally being available four to six hours per day. As one citizen said, “When it is over 100
        degrees at night and you have no electricity and no air-conditioning, it is hard to think
        about the benefits of democracy; show me electricity, and I will show you democracy.”
           Lastly, many existing facilities were primitive in nature. For example, many rural
        schools did not have bathroom facilities or electrical lighting. Thus school rehab pro-
        jects focused on adding the basics such as bathrooms and electricity.


        Stakeholder Management
        When the program began, PMOs key stakeholders were the Iraqi ministers in
        Baghdad. This quickly changed, and the following other stakeholders emerged:

        ● Local politicians. The governors of the governates and the mayors of the cities all
          wanted to know what would happen when in their locality. They were very support-
          ive of the rebuilding effort and had some specific goals, such as (1) to attract as
          many projects as possible in their locale, (2) to drive some of the construction sub-
          contracts to businesses in their locale, and (3) to be part of the process.
        ● The Multi-National Forces (MNFs). For military purposes, Iraqi was divided into six
          geographic segments with an MNF led by a general in charge of each segment. The
          MNFs believed that the quickest way to win the peace and the hearts and minds of the
          Iraqi people was to build projects as fast as possible. Thus each general was vitally inter-

          ested in what projects would be done in his area and when the project would start.
        ● Army Corp of Engineers. The corp was in charge of construction management on all
          2500 projects, and as such, it was imperative for the PMO to create and maintain good
          communications with corp offices throughout Iraq.
        ● Local contractors. Local contractors throughout Iraq wanted to be involved in the
          rebuilding effort, and questions continuously arose relating to how a local contractor
          could be awarded work. While the DB contractors were the only groups that could sub-
          contract work, the questions from the local contractors usually would come to the PMO.
          It then became an ongoing effort to link local contractors and the collation DB contrac-
          tors together. To support the local contractors, the civil affairs function of the MNFs
          often would set up business centers in cities to create a place for the DB contractors to
          come and meet with local contractors.

        Building a Regional Organization

        When started in late 2003, the CPA was located in Baghdad only. As the program was
        implemented in the spring of 2004, it was necessary to build a regional or outreach program
   245   246   247   248   249   250   251   252   253   254   255