Page 154 - How To Implement Lean Manufacturing
P. 154

132    Cha pte r  Se v e n


                   QED Motors Future State                                           Production
                                                                                     Planning
                                                                                      (local)













                                        Note the significant change
                       Value Stream Summary                            Note Planning Changes…
                                        in the process lead time….
                      Total Lead Time  20.38  Hrs  From 210 hrs to 20 hrs!!!  1-2 day delay eliminated
                                                                       2-Shipping schedule sent to storehouse only
                      Total Processing  0.98  Hrs                      3-Production triggering and leveling done by
                         Time                                          kanban
                                                               2x/Shift
                        Takt Time  7.09  Min                           4-Wire coil supply to the Coil Insertion cell is
                                                                       now done by a kanban pull system
                                                                       5-Heijunka board at Coil Insertion is updated
                                                                       twice per shift and model mix leveled
                                                                           Note Process Changes
                                                                           1-Production is balanced at 50/50 mix
                                                                           2-Press and Hipot are combined for better process
                     Coil Wind                                             balance
                                                                           3-ProcessWIP hasinvnentorylimits and
                                                                           segregations to synchronize flow, Polish process is
                    CT  4.5 Min                                            eliminated
                                                                           4-CNC lathe, old bottleneck at 9 min. Now has 6.5
                    CO  6  Min
                                                                           min cycle time, CO reduced from 45 to 11 minutes
                   Operators  3  Stf
                    Stator Prep   Coil Insertion  Lace        Press & HiPot   Preheat       Varnish
                    CT Lg  6.5 Min  Max  CT Lg  13.5 Min  Max  CT  5.7 Min  Max  CT  6  Min  Max  CT  90 Min  Max  CT  40 Min
                             6  Unt        5  Unt         4  Unt       24 Unt  Batch  27 Unt  Batch
                   CT Sml  6  Min  Cell Lg  2  Unt  Operators  5  Stf  Scrap  3.2  %  18 Unt   9  Unt
                                                                             Size          Size
                    CT  6.25 Min  CT Sml  13.0 Min            Operators  1  Stf  Operators  1  Stf  Operators  0  Stf
                   Operators  2  Stf  Cell Sml  2  Unt
                                   CT  6.61 Min
                                 Operators  14  Stf


                            112 Min        46 Min        30 Min        165 Min       120 Min
                     6.25 Min      6.61 Min      5.70 Min       6.00 Min      5.00 Min      4.44 Min
                    Mths  Days  Shifts  Hrs
                    21.5  2  9.75  60
                    Days  Shifts  Hrs  Min
                   Drawn in: eVSM Software (www.evsm.com)

               FIGURE 7-10  Future state value stream map, QED motors.
   149   150   151   152   153   154   155   156   157   158   159