Page 276 - How To Implement Lean Manufacturing
P. 276

Using the Pr escription—Thr ee Case Studies     253


                    We Start Production
                    Work started and went exceedingly smooth. Quite frankly, since they had been forced
                    into doing this, I expected resistance, but surprisingly none occurred—instead, the
                    whole group was cooperative. With only four pieces at each station, the line filled
                    quickly and production was moving smoothly at about 40 seconds cycle time. Station 4
                    was clearly the bottleneck. It was extremely awkward for the operator to transfer her
                    part to Station 5. The supervisor recognized the problem, had a small sheet metal slide
                    made, and installed it. By noon, the line was producing at less than takt. In fact, by the end
                    of the run, the line was producing smoothly and comfortably at a 28-second cycle time
                    and the 800-unit batch was, for the first time, completed in less than one shift. We had
                    only one major problem. The materials supply and kanbans were set up to supply at the
                    older slower rate, so the materials handler had to make many emergency runs to keep
                    up with the cell. Recall that they had started at the supply end with detailed plans for
                    every part, so when we improved the cell, all their part plans needed to be redone.

                    Quick Early Gains Are Huge
                    In summary, an 800-unit shipment that had previously taken a ten-person cell over two
                    complete shifts to complete, was now being done in less than one shift with only five
                    people. Hallelujah! (See Table 16-6.) It does not get much better than this when you deal
                    in process improvements. All this without any capital expenditures, and no quality or
                    other downside issues at all! I was pleased. Very pleased.
                       A large uninteneded consequence resulted from this process improvement. As it
                    turns out, this controller was one of a family of controllers that were all made on this
                    work cell. Plus, the new layout could be used for the entire family. The ten-person
                    cell would normally work 24 hours, 7 days a week to make the demand for the entire
                    family. Now they could produce the demand in less than four days with only five
                    operators. The savings was a net reduction of 30 man days of work per day, forever.

                    No “Lean Hero of the Month” Here
                    Wow, think about this. The GM was so proud of his reduction of materials handlers by
                    nine persons, I figured I would be hailed as the Lean hero of the month. Instead, every-
                    one just yawned and didn’t even say “thanks.” In fact, the lead industrial engineer, who
                    resisted the suggested improvements in the first place, now said, “We had planned on
                    doing that all along.” So I guess my entry into the “Lean Hero of the Month Club”
                    would have to wait a while. But the cell was certainly setting new performance stan-
                    dards and was ready for a new time study, and also ready to be rebalanced to achieve
                    further gains.


                      Metric            Original Case     Leaned Process    % Improvement
                      First piece Lead   4.5 hrs          9 min.            97% reduction
                      Time
                      Batch Lead Time   20 hrs            8.5 hrs           58% reduction
                      Space utilization  425 sq. ft.      160 sq. ft.       62% reduction
                      Operators per cell  10              5                 50% reduction
                      Labor costs/unit  15 min/unit       3.19 min/unit     79% reduction
                    TABLE 16-6  Gains Summary, Zeta Cell
   271   272   273   274   275   276   277   278   279   280   281