Page 345 - Hydrocarbon Exploration and Production Second Edition
P. 345

332                                                 Cost Estimation and Budgets


                      100
                       90

                       80

                       70
                     Progress in %  50
                       60



                       40
                       30

                       20

                       10


                 Days          1        2        3        4        5        6
              % Completed     15       20       15       10       20        20
                per day
              % of project    15       35       50       60       80       100
               completed
          Figure 13.7  Progress plot (or ‘S’-Curve).


             Plots such as this can be used to compare actual to planned progress. If progress
          is delayed at any point, but the completion date cannot be slipped, the plot can be
          used to determine how many extra resource units have to be employed to complete
          the project on time.



               13.3. Cost Estimation and Budgets

               At each phase of a project, cost information is required to enable decisions
          to be taken. In the conceptual phase these estimates may be very approximate
          (e.g.+40% accuracy), reflecting the degree of uncertainty regarding both reservoir
          development and surface options. This is sometimes referred to as an ‘order of
          magnitude cost estimate’. As the project becomes better defined the accuracy of
          estimates should improve.
             An appropriate estimate of technical cost is important for economic analysis.
          Underestimating costs may lead to funding difficulties associated with cost overruns,
          and ultimately, lower profitability than expected. Setting estimates too high can kill
          a project unnecessarily. Costs are often based on suppliers’ price lists and historical
          data. However, many recent oil and gas developments can be considered pioneering
   340   341   342   343   344   345   346   347   348   349   350