Page 344 - Hydrocarbon Exploration and Production Second Edition
P. 344

Project and Contract Management                                       331


                                                      DAYS
                       Time
                Activity         1        2         3        4        5        6
                                 3
                     A
                                          1
                     B
                                          4         2        2
                     C
                                                                      4        4
                     D

                  TOTAL          3        5         2        2        4        4

             Figure 13.6  Bar chart with resource loading.


             Table 13.1  Resource weighting matrix
               Activity              Weight per Day              Weight per Activity (%)


                          1      2     3      4     5      6
               A         15.0                                             15
               B                      5.0                                  5
               C               20.0   10.0  10.0                          40
               D                                   20.0  20.0             40
               Total     15%   20%    15%   10%    20%   20%             100



                The bar chart below is a representation of the network shown in Figure 13.4.
             In addition the chart has been used to display the resource loading (Figure 13.6).
                The bar chart indicates that activity ‘B’ can be performed at any time within
             days 2, 3 and 4, without delaying the project. It also shows that the resource loading
             can be smoothed out if activity ‘B’ is performed in either day 3 or 4, such that the
             maximum loading in any period does not exceed 4 units. Resource units may be,
             for example, ‘man hours’ or ‘machine hours’.
                The resource loading can be represented in percentage terms (see Table 13.1)to
             give an indication of the resource ‘weighting’ distribution on a daily basis and per
             activity (note that activity ‘B’ has been moved to day 3 to smooth resource loading).

             13.2.3. ‘S’-curves

             By plotting the cumulative resource weighting against time, the planned progress
             of the project can be illustrated, as shown in Figure 13.7. This type of plot is often
             referred to as an ‘S’-Curve, as projects often need time to gain momentum and slow
             down towards completion (unlike the example shown).
   339   340   341   342   343   344   345   346   347   348   349