Page 343 - Hydrocarbon Exploration and Production Second Edition
P. 343

330                                                       Planning and Control



                   1 Day                   1 Day





                     Activity
                                          3 Days                  2 Days
                     Critical Path
          Figure 13.4 Project planning network.

                          Earliest                   Earliest
                         Start Date                   Finish
                            2                          5
                                                                Duration
                   Activity
                   Number 1
                                       Description
                                        of Activity        3


                            3                          6
                           Latest                     Latest
                         Start Date                   Finish
          Figure 13.5  Activity symbol convention.


          identified. All activities are given a duration and the longest route through the
          network is known as the critical path.
             In Figure 13.4, the relationship between four activities of different duration is
          shown. In this case the critical path is indicated by the lower route (6 days), since the
          last activity cannot start until all the previous activities have been completed.
             In reality all activities are listed and dependency relationships are identified.
          Activities are given a duration, and an earliest start and finish date is determined,
          based on their dependency with previous activities. Latest start and finish dates
          (without incurring project delays) can be calculated once the network is complete,
          and indicate how much ‘play’ there is in the system.
             A typical ‘activity symbol’ convention is shown in Figure 13.5. Other informa-
          tion that may be included in a network is: milestones (e.g. first oil), weather
          windows and restraints (e.g. permit to continue requirements).
             Once a network has been constructed it can be reviewed to determine whether
          the completion date and intermediate key dates are acceptable. If not, activity
          duration reductions have to be sought, for example, by increasing manpower or
          changing suppliers.


          13.2.2. Bar charts
          Whilst network analysis is a useful tool for estimating timing and resources, it is not
          a very good means for displaying schedules. Bar charts are used more commonly to
          illustrate planning expectations and as a means to determine resource loading.
   338   339   340   341   342   343   344   345   346   347   348