Page 340 - Hydrocarbon Exploration and Production Second Edition
P. 340

Project and Contract Management                                       327


                Providing a project is viable, resources are available and risk levels acceptable,
             work can continue on preliminary design and tighter cost estimates. The object of the
             preliminary design phase is to prepare a document that will support an application
             for funds. The level of detail must be sufficient to give fund holders confidence
             that the project is technically sound and commercially robust, and may also have to
             be used to gain a licence to proceed from government bodies. Tried and tested
             engineering issues may not need a great deal of elaboration, but issues with a high
             novelty value have to be identified and clearly explained. If work is subsequently
             contracted out the document can form the basis for a tender. This phase is also
             referred to as front end engineering design (FEED).
                Once a project has been given approval then detailed design can begin. This phase
             often signals a significant increase in spending as teams of design engineers are
             mobilised to prepare detailed engineering drawings. It is also quite common for oil
             companies to contract out the work from this stage, though some company
             staff may continue to work with the contractor in a liaison role. The detailed
             engineering drawings are used to initiate procurement activities and construction
             planning. By this stage the total expenditure may be 5% of the total project budget,
             and yet around 80% of the hardware items will have been specified. The emphasis at
             the detailed design stage is to achieve the appropriate design and to reduce the need
             for changes during subsequent stages.
                Procurement is a matter of getting the right materials together at the right time
             and within a specified budget. For items which can be obtained from a number of
             sources a tendering process may appropriate, possibly from a list of company approved
             suppliers. Very exotic items, or items which are particularly critical, may be
             acquired through a single source contract where reliability is paramount. Complex
             items such as turbines will often be accompanied by test certification which has
             to be checked for compliance with performance and safety standards. Equipment
             must be inspected when the company takes delivery, to ensure that goods have not
             been damaged in shipment. The procurement team may also be responsible for
             ensuring that the supply of spare parts is secure. Spending at this stage can range
             anywhere from 10 to 40% of the total project cost.
                The character of a project construction phase can vary considerably depending
             on the nature of the contract. The construction of a gas plant in a rural setting
             will raise very different issues from that of a refurbishment project on an old
             production platform. Construction activities will normally be carried out by
             specialised contractors working under the supervision of a company representative
             such as a construction manager (or resident engineer). The construction manager is
             responsible for delivering completed works to specification and within time and
             budget limits. When design problems come to light the construction manager must
             determine the impact of changes and co-ordinate an appropriate response with the
             construction contractor and design team.
                As construction nears completion the commissioning phase will begin. The
             objective of the commissioning phase is to demonstrate that the facility constructed
             performs to the design specification. Typically a construction team will hand over
             a project to an operating team (which may be company staff) once the facility or
             equipment has been successfully tested. The receiving party will normally confirm
   335   336   337   338   339   340   341   342   343   344   345