Page 246 - Industrial Power Engineering and Applications Handbook
P. 246

Winding insulation and its maintenance 9/225
         9.5.3  Making-up of the insulation level in large   resistance readings. It will not be less than  1.5 for class
              machines (1000 kW and above)              A, 1.75 for class E and 2 for class B insulations for the
                                                        windings  to be regarded  as suitable for a high-voltage
         IEEE  43  places  special  emphasis  on  determining  the   test  or  actual  operation.  This  index  is  based  on  the
         insulation condition of such machines before energizing   phenomenon  that the insulation resistance of a winding
         and even before conducting a high-voltage test. This can   rises with the duration of application of the test voltage.
         be determined by the insulation test as noted below.   The rise is rapid when  the voltage  is first  applied  and
                                                        then  it almost stabilizes with  time,  as noted  in Figure
         Insulation resistance test                     9.4. For instance, after 30 seconds of the applied voltage
                                                        this resistance may be too small, of the order of only a
         Insulation  resistance  of  the  windings  is  a  measure  to   fraction of the final value. As a rough guide, the insulation
         assess the condition of insulation and its suitability for   resistance of a dry and normal winding may also continue
         conducting  a  high-voltage  test  or  for  energizing  the   to rise in the first few minutes  after application of the
         machine.  A  low  reading  may  suggest  damage to  the   test  voltage  before  it stabilizes. Normally  it  may  take
         insulation,  faulty drying or impregnation or absorption   10-15  minutes to reach  a steady state. If  the windings
         of moisture. The insulation resistance may be measured   are wet or dirty the steady condition may be achieved
         according to the procedure laid down in IEEE 43 between   within one or two minutes of application of test voltage.
         the open windings and between windings and the frame   These test results are then compared with similar test
         by employing a direct-reading ohm meter (meggar). The   data obtained from the manufacturer on similar windings
         ohm  meter  may  be  hand-operated  or power-driven  or   carried  out  during  manufacture.  If  the  manufacturer’s
         equipped  with  its  own  d.c.  source.  500 V  d.c.  is  the   original test results are available, the results obtained at
         recommended  test  voltage  for an  insulation  resistance   site can be quickly compared and the condition of the
         test for all voltage ratings, as noted later. The recommended   insulation assessed easily and accurately. If the test facility
         minimum insulation resistance of the machine is obtained
         by the following empirical formula:            to obtain test results at  1 minute and  10 minutes is not
                                                        available, the results may also be obtained for 15 seconds
         R,  = kV+ 1                             (9.1)   and 60 seconds and a graph plotted as shown in Figure
         where                                          9.5(a) to determine the polarization  index.
         R,  = recommended  minimum  insulation  resistance  in   From these insulation tests several test data for 1 minute
             MR (meg ohms) of the entire machine windings,   and  10 minutes  can be obtained during  the process  of
             at 40°C or 1 MR per  1000 V plus  1 MQ, and   heating  over a few hours  and a graph  plotted  for time
         kV = rated machine voltage in kV               versus insulation resistance. This graph is of great assistance
                                                        in determining the state of the windings before energizing.
          The winding insulation resistance to be used for com-   Heating or cleaning-up of the windings should continue
         parison  with the recommended minimum value (R,)  is   until the polarization index matches the reference value
         the observed insulation resistance obtained by applying
         a  d.c.  voltage  to  the  entire  windings  for  one  minute,
         corrected to 40°C. In practice, motors having insulation
         resistance readings as high as ten to a hundred times the
         minimum recommended value R,  are not uncommon.
          At  site,  when  commissioning  a  new  or  an  existing
         motor after a long shutdown, it must have a minimum   1000
                                                           800
         insulation level according to equation (9.1). An  11 kV   600
         motor, for instance, must have a minimum insulation of
         12 MQ. In normal practice, it is observed that when first  1 400
         measured  the  resistance  reading  may  show  more  than   3
         the minimum value and may mislead the operator, while   $200
         the winding condition may not be adequate for a high-   0
         voltage test or an actual operation. One must therefore   24
        ensure that the winding condition is suitable before the   .$  100
         machine  is  put  into  operation.  For  this  purpose,  the   F!  80
                                                         C
        polarization  index  (PI), which  is  determined  from  the   .s  60
         insulation test data only as noted below, is a useful pointer.   9
                                                         ?  40
         It must be evaluated at site while conducting the insulation   I
         test  then  compared  with  the  manufacturer’s  reference
        data for the machine to assess the condition of insulation   20
        at site and its suitability for operation. This is usually a
         site test, but to establish a reference record of the machine,   10   Time (minutes) -
         it is also carried out at the works on the completed machine   0.1   0.2   0.4  0.7 1.0   2.0   4.0  7.0 10.0
         and test records furnished to the user.
        Polarization index                              Figure 9.4  Variation of insulation resistance with time for
         This  is the  ratio  of  10 minute  to  1  minute  insulation   class B insulation
   241   242   243   244   245   246   247   248   249   250   251