Page 448 - Industrial Power Engineering and Applications Handbook
P. 448

14/422 Industrial Power Engineering and Applications  Handbook
       disturbances as well as the recommended tests and their   For routine tests: class  1.0 accuracy or better, and
       procedures to verify the suitability of critical structures,   for type tests: not below class 0.5 accuracy.
       equipment and devices for locations that are earthquake-
       prone.                                         The current transformers and potential transformers must
                                                      conform to IEC 60044-1 and IEC 60044-2 respectively.
       14.2.4  Field tests                            Instrument  transformers  with the  following  accuracies
                                                      must be used.
       Generally the following tests may be carried out at site
       after installation  and before energizing an assembly:   For routine tests: Class  1 accuracy
                                                        For type tests: Class 0.5 accuracy
       1  Checking for any human error as described in Section
         14.2.2.                                      14.3.2 Verification of insulation resistance
       2  Visual inspection of  the switchgear assembly
       3  Inspection of  electrical wiring (see Section  14.2.2)   This test is covered under field tests, Section  14.5(4).
       4  Verification of insulation resistance  or measurement
         of  the  leakage  current,  both  before  and  after  the   14.3.3 Verification of dielectric properties
         dielectric test, when an HV test is being conducted at
         site.                                        Power frequency voltage withstand or HV test
       5  Verification of dielectric properties, limited to power
         frequency voltage withstand test. This test is neither   The  test  voltage  must  be  as  close  to  a  sine  wave  as
         mandatory nor recommended, but may be required if   practicable and frequency as noted in column 3 of Tables
         a modification is carried out in the switchgear assembly   14.1 and  14.2, for  series I1 and Table  13.2 for  series I
         at site.                                     voltage systems, and applied for one minute as follows:
                                                      1  If  relays, instruments  and other auxiliary apparatus,
       14.3  Procedure for type tests                   have a voltage other than the main voltage, they should
                                                        be disconnected from the main circuit, while conduc-
       Below we outline the procedure for conducting the above   ting this test and tested separately, according to their
       tests at the manufacturer's  works.              voltage rating as shown in Table 14.3.
                                                      2  All the CT (current transformer) secondaries must be
       14.3.1  Electrical measurements                  shorted  and grounded  while  conducting  the test  on
                                                        the  main  circuit. This condition  is redundant  while
       Selection of testing instruments                 conducting test on the auxiliary circuit.
                                                      3  PT (potential transformer) windings must be disconnec-
       The instruments used for electrical measurements  must   ted by removing the control fuses from its both sides.
       conform to IEC 60051-1. Instruments with the following   4  The test voltage at the moment of application should
       accuracies must be used:                         not exceed 50% of the rated test value and should be





       Nominal system   Rated maximum   One-minute power frequency  voltage withstand   Standard lightning impulse
       voltage       system voltage   at a frequency not less than the rated 60 Hz   (1.2/50 ,us) voltage
                                    (phase to ground)                          withstand (phase to ground)
       I             2              3                                          4

       kV (r.m.s)    kV (r.m.s.)    kV (r.m.s.)        kV (r.m.s.)             kV beak)


                                    List I   List I1   List I    List I1       List I      List I1
        4.16          4.76           19       19         -        -             60          60
        7.20          8.25          26        35        24        30            75          95
       13.80         15.0           35        50        30        45            95          110
       23.0          25.8           50        70        45        60           125         150

       34.5          38.0           70        95        60        80           150         200
        -            48.3           120       120      100       100           250         250
       69.0          72.5           160       160      140       140           350         350
   443   444   445   446   447   448   449   450   451   452   453