Page 177 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 177

Coal-fired power plant Chapter  8 153


             8.9.3  Install and weld attemperators, superheater, and reheat
             components sheet 3


                                                      Installation man-hour
                                                  Historical      Estimate
                                                MH     Unit   Qty  Unit  BM
             Install and weld attemperators, superheater,                0
               and reheat components
             Final secondary superheater
             Tubes—connecting                   1.65   EA     0    EA    0
             Tubes—sections                     7.00   Ton    0    Ton   0
             Headers                            15.00  Ton    0    Ton   0
             Weld tubes to header stubs—(3-1/2 < BW  4 00  5.90  EA  0  EA  0
                                     00
               TIG) (2001–2600) psi
             Fit and weld filler bar at tube welds  1.00  Space  0  Space  0
             First and second stage attemperators
             Spray type—complete with body and internals  20.00  Ton  0  Ton  0
               (excludes welding)
             Drum type—complete with internals, p&v,  32.00  Ton  0  Ton  0
               support (excludes welding)
             Tubes (4-1/2 welded to stub and 4 expand in
                                     00
                      00
               drum, weld to hdr)
             4 OD, expand tubes in drums (1800 psi)  4.00  EA  0   EA    0
              00
             Weld tubes to header stubs—(4 < BW   4-1/2  6.50  EA  0  EA  0
                                  00
               TIG) (2001–2500) psi
             Platen secondary superheater-pendant/inverted
               loop
             Headers                            65.00  Ton    0    Ton   0
             Supports—rods                      65.00  Ton    0    Ton   0
             Tube sections                      20.00  Ton    0    Ton   0
             Tube section supports              20.00  Ton    0    Ton   0
             Saturated connections              35.00  Ton    0    Ton   0
             Mounting seals                     90.00  Ton    0    Ton   0
             Seals                              175.00  Ton   0    Ton   0
             Weld tubes to header stubs—3-1/2 < BW  4 00  5.90  EA  0  EA  0
                                     00
               TIG) (2001–2600) PSI