148   Industrial process plant construction estimating and man-hour analysis


            8.8 Coal-fired boiler estimate data
            8.8.1 Install drum, erect headers, panels, furnace wall, roof tubes,
            weld tubes/panels sheet 1

            Description                                         MH     Unit
            Install steam drum
            Drums—include straps and/or U-bolts: steam drum (200,001 lb   Weight  9.00  Ton
                300,000 lb)
            Steam drum trim piping                              160.00  Boiler
            Drum internals—remove and reinstall                 136.00  Boiler
            Set rigging for hoisting assemblies                 60.00  Boiler
            Hoist into place                                    1.50   Ton
            Erect headers and wall panels; fit and weld water wall panels
            Boiler sidewall, furnace front wall, roof, sidewall, and rear wall tubes
            Headers—loose                                       15.00  Ton
            Wall panels—shop assembled without headers          10.00  Ton
            Weld tubes—panel to panel—(2 < BW   2-1/2 TIG) (2001–2600) psi  4.20  EA
                                              00
                                   00
            Fit and weld filler bar at tube welds               1.00   Space
            Weld tubes to header stubs—(2 < BW   2-1/2 TIG) (2001–2600) psi  4.20  EA
                                  00
                                             00
            Fit and weld filler joining membrane panels         0.70   LF
            Tubes—loose, furnace including screen               1.40   EA
            Weld tubes to header stubs—(2-1/2 < BW   3 TIG) (2001–2600) psi  4.60  EA
                                     00
                                             00
            Furnace rear wall tubes (wall panel—membrane)       12.00  Ton
            Install and weld membrane and scallop bars on nose tubes  2.30  Ton
            8.8.2 Install and weld attemperators, superheater, and reheat
            components sheet 2

            Description                                         MH     Unit
            Install and weld attemperators, superheater, and reheat components
            Tubes—connecting                                    1.65   EA
            Tubes—sections—final secondary superheater          7.00   Ton
            Headers                                             15.00  Ton
            Weld tubes to header stubs—(3-1/2 < BW   4 TIG) (2001–2600) psi  5.90  EA
                                     00
                                             00
            Fit and weld filler bar at tube welds               1.00   Space
            Spray type—complete with body and internals (excludes welding)  20.00  Ton
            Drum type—complete with internals, piping, valves, and supports  32.00  Ton
              (excludes welding)
            4 OD, expand tubes in drums (1800 psi)              4.00   EA
             00
            Weld tubes to header stubs—(4 < BW   4-1/2 TIG) (2001–2500) psi  6.50  EA
                                  00
            Headers                                             65.00  Ton
            Supports—rods                                       65.00  Ton
            Tube sections—platen secondary superheater-pendant/inverted loop  20.00  Ton
            Tube section supports                               20.00  Ton
            Saturated connections                               35.00  Ton
            Mounting seals                                      90.00  Ton
            Seals                                               175.00  Ton