Page 174 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 174
150 Industrial process plant construction estimating and man-hour analysis
8.8.4 Tubes, down comers, accessories, burner, soot blowers,
economizer sheet 4
Description MH Unit
Automatic lighters include welding 6.00 EA
Soot blower SB, SB with PVF 151.00 EA
Pressure reducing station 70.00 EA
Trays and channels for supporting tubing 18.00 EA
Tubing for automatic sequential air operation 40.00 EA
Air compressor and/or receiver 18.00 Ton
Auto sequential panel or air master controller 86.00 Panel
IK structural supports 6.00 Blower
Tube sections 7.00 Ton
Headers 15.00 Ton
Integral support steel 28.00 Ton
Set rigging for hoisting assemblies 60.00 Boiler
Hoist into place 1.50 Ton
00
00
Weld tubes to header stubs—(2 < BW 2-1/2 SMAW (2001–2600) psi 3.10 EA
Fit and weld filler bar at tube welds 1.00 Space
Casing and hoppers including doors 55.00 Ton