Page 176 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 176

152   Industrial process plant construction estimating and man-hour analysis


            8.9.2 Drum, headers, panels, furnace wall, roof tubes, weld tubes/
            panels sheet 2


                                                      Installation man-hour
                                                  Historical     Estimate
                                                MH     Unit  Qty  Unit   BM
            Furnace roof/floor tubes
            Headers—loose                       15.00  Ton   0    Ton    0
            Tubes—loose, furnace including screen  1.40  EA  0    EA     0
            Weld tubes to header stubs—(2-1/2 < BW   3 00  4.60  EA  0  EA  0
                                     00
              TIG) (2001–2600) psi
            Furnace sidewall tubes
            Headers—loose                       15.00  Ton   0    Ton    0
            Wall Panels—shop assembled without headers  10.00  Ton  0  Ton  0
            Weld tubes—panel to panel—(2 < BW   2-1/2 00  4.20  EA  0  EA  0
                                  00
              TIG) (2001–2600) psi
            Fit and weld filler bar at tube welds  1.00  Space  0  Space  0
                                  00
            Weld tubes to header stubs—(2 < BW   2-1/2 00  4.20  EA  0  EA  0
              TIG) (2001–2600) psi
            Fit and weld filler joining membrane panels  0.70  LF  0  LF  0
            Furnace rear wall tubes
            Furnace rear wall tubes (wall panel—membrane)  12.00  Ton  0  Ton  0
            Furnace rear wall tubes (loose)     1.40   EA    0    EA     0
            Weld tubes—panel to panel—(2 < BW   2-1/2 00  4.20  EA  0  EA  0
                                  00
              TIG) (2001–2600) psi
            Fit and weld filler bar at tube welds  1.00  Space  0  Space  0
            Weld tubes to header stubs—(2 < BW   2-1/2 00  4.20  EA  0  EA  0
                                  00
              TIG) (2001–2600) psi
            Fit and weld filler joining membrane panels  0.70  LF  0  LF  0
            Install and weld membrane and scallop bars on  2.30  Ton  0  Ton  0
              nose tubes
   171   172   173   174   175   176   177   178   179   180   181