            8.6 General scope of field work required for each coal-fired
            boiler sheet 5


               Scope of Work-Field Erection
               Pressure Parts
               Supply and Riser Tubes, Down comers, Boiler Equipment, Burners,
               Economizer and Diamond Soot blowers
               Bare Tube Economizer
               Tube sections
               Headers
               Integral support steel
               Set rigging for hoisting assemblies
               Hoist into place
                                                                  00
               Weld tubes to header stubs—(2 00  < Ring Weld   2-1/2 ) SMAW
               (2001–2600) psi
               Fit and weld filler bar at tube welds
               Casing and hoppers including doors

               Supply and Riser Tubes
               Headers
               Tubes—make up or supply
               Tubes—riser
                                         00
                                                      00
               Weld tubes to header stubs—(4 < BW   4-1/2 TIG) (2001–2600) psi
               Down Comers
               Install down comer
               Diameter weld, girth
               Diameter weld, ring
               Diameter weld, ring