234 Industrial Process Plant Construction Estimating and Man-Hour Analysis


            11.9.3 Air cooled condenser installation decreased quantities
            estimate


            Description                 MH    Qty    Unit  Qty    Unit  IW
            Upper structure A-frame steelwork                          267.0
            Erect and temporarily bolt structural  2.50  7.25  Ton  7.25  Ton  18.1
              steel
            Seal plate                  2.00  20.00  EA    20.00  EA   40.0
            Access door frame           10.00  1.00  EA    1.00   EA   10.0
            Cut sheeting to size        0.002  532.10  SF  532.10  SF  1.1
            Place sheeting              0.23  357.00  SF   357.00  SF  80.5
            Fix sheeting with flashing and caulk  0.05  532.10  SF  532.10  SF  26.6
            Tack or screw sheeting      1.00  21.25  EA    21.25  EA   21.3
            Install access door         10.00  1.00  EA    1.00   EA   10.0
            Pipe hanger with turnbuckle and  10.00  2.00  EA  2.00  EA  20.0
              clevis
            Install steam saddles       10.00  3.00  EA    3.00   EA   30.0
            Bolt connection             0.15  62.90  EA    62.90  EA   9.4




            11.10 Comparison and graphic analysis of data


            Comparison of estimated direct craft man-hours         Man-hours
            Equipment quantities are decreased; estimated man-hours are decreased  1  267
            MHc ¼ field erection man-hours based on historical data  2  295
            Equipment quantity is increased; estimated man-hours are increased  3  325


                     400
                     300
                    Man hours  200  y = 29.196x + 237.29    Series1

                                2
                               R  = 0.9991
                                                            Linear (Series1)
                     100
                       0
                        0       1      2      3       4
            FIG. 11.10.1 Comparison of estimate man-hours.

               Estimate is based on historical data from field erection of A-frame structure
            in a solar power plant (Fig. 11.10.1), and the scope and quantity differences can
            be identified and the impacts estimated; therefore,
                                    MHᵦ   MH c   MHₔ