Sample estimates Chapter 11 235
The proposed unit is based on the estimator’s quantity takeoff, and erection
quantities are either (+ or ) 15% direct proportion (straight-line graph); com-
parison method quantities are directly proportional to estimate MHs. Whenever
one variable increases or decreases, the other increases or decreases and
vice versa.