Page 282 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 282

Statistical applications to construction Chapter  12 261


                                                         P
                Calculate the expected value for each risk: E(X)¼  pX
             Risk

             1    Weather                 E(X) ¼ SUMPRODUCT (H71,I71)   $22,500
             2    Material                E(X) ¼ SUMPRODUCT (H72,I72)  $2,750
             3    Productivity            E(X) ¼ SUMPRODUCT (H73,I73)   $30,000
                  Project expected value  E(X) ¼ K71 + K72 + K73      $49,750
                  If all risk occur, the project   $49,750
                  would lose



             12.9.2 Range method

             The range method has three estimates, lowest, most likely, and highest for each
             major cost element. This forms the basis for range estimating.
                The mean and variance for each of the three single cost elements are calcu-
             lated as

                                   EC i ¼ L +4M + Hð  Þ=6
                                    ðÞ
                                                    ^
                                     ðÞ
                                   var C i ¼ H  Lðð  Þ=6Þ 2
                where E(Cᵢ) ¼ expected cost of distribution i, i ¼ 1, 2, …, n
                L ¼ lowest cost or best-case estimate of cost distribution
                M ¼ modal value or most likely estimate of cost distribution
                H ¼ highest cost, or worst-case estimate of cost distribution
                var(Cᵢ) ¼ variance of cost distribution i, I ¼ 1, 2, …, n, dollars 2
             The elements are assumed to be independent of each other and are added; then,
             the new distribution of the total cost is approximately normal. This follows from
             the central limit theorem. The mean of the sum is the sum of the individual
             means, and the variance is the sum of the variances:

                                      ð
                               ð
                                             ð
                                                       ð
                              ECrÞ ¼ EC 1 Þ + EC 2 Þ + ⋯ + EC n Þ
                                               ð
                                      ð
                                                           ð
                          var CrÞ ¼ var C 1 Þ + var C 2 Þ + ⋯ + var C n Þ
                             ð
                where E(Cr) ¼ expected total cost of independent subdistributions i
                var (Cr) ¼ variance of total cost of independent subdistributions i
             The probability is calculated using
                                                      1
                                          ð
                                Z ¼ UL ECrÞ= var Crފ   2
                                              ½
                                                  ð
                where Z ¼ value of the standard normal distribution, Appendix A
                UL ¼ upper limit of cost, arbitrarily selected
   277   278   279   280   281   282   283   284   285   286   287