Page 282 - Introduction to Mineral Exploration
P. 282

11: PROJECT EVALUATION  265


                 plant, will have demonstrated that a product  the major factors that may have an impact
                 can be extracted using a viable process. The  upon the reserve estimate. This will help quan-
                 mine infrastructure and labor requirements,  tify the risk associated with the reserves,
                 and the impact of the potential mine on the en-  which at this stage will fall within the compa-
                 vironment will have been evaluated. Detailed  ny’s acceptable risk category. If the company is
                 evaluation of capital and operating costs can  approaching a financial institute to borrow the
                 be established to ±25%. These figures will be  capital that will be required to bring the mine
                 used, along with a preliminary mine schedule,  on stream, these risk factors will be assessed
                 in a financial and commercial evaluation. A   in detail. Often, financial institutes use inde-
                 number of sensitivities will have been assessed,  pendent consultants to audit the resource and
                 including alternative methods of mining and  reserve estimates. The reserves will be based
                 processing the mineralisation, and the effects  upon a final mine design. This design will
                 of various levels of output. The integration of  provide the information to enable the company
                 social and environmental aspects is most im-  to request bids for detailed engineering studies.
                 portant in the consideration of options for major  Similarly, a final process flow sheet will have
                 project decisions. Findings from the social and  been developed. Costs will have been devel-
                 environmental baseline studies are used as the  oped to ±15%.
                 basis to predict and evaluate the likely effects
                 or impacts, whether negative or positive. The
                 option that demonstrates the highest value   11.4.5 Detailed engineering
                 with acceptable (lowest) risk will be selected  Once the decision is taken to proceed to
                 as demonstrably viable. Such a study can cost  detailed engineering, costs will be developed to
                 several hundred thousand dollars.            ±10%. The project is almost certain to progress
                                                              to a mine. This is the final stage before major
                                                              capital expenditure is incurred and involves
                 11.4.4 Feasibility study
                                                              producing detailed plans and work schedules
                 The aim of the feasibility study is to confirm  so that orders can be placed for equipment
                 and maximize the value of the preferred tech-  and the mine development can begin. These
                 nical and business options identified in the  investigations are thorough, penetrating, and
                 pre-feasibility study stage.                 usually completed by outside consultant com-
                   During the feasibility study the environ-  panies who specialize in this type of work.
                 mental and other statutory approvals processes,  Such a study usually takes several months
                 commenced during the pre-feasibility study,  or years, depending upon the initial database,
                 will continue but at an accelerated pace. Con-  and can cost several million dollars for a large
                 sultations and negotiations with local commu-  project.
                 nity groups, landowners, and other interested
                 parties will proceed to the point of basic agree-
                 ment. Social and environmental impact assess-  11.5  MINERAL PROJECT VALUATION AND
                 ments will be required that meet statutory and    SELECTION CRITERIA
                 company requirements. The timing of formal
                 submissions for permitting and other statutory  Previous sections have considered the value of
                 processes needs careful consideration. Sub-  mineralisation in absolute terms (i.e. a sum of
                 mission too early may prematurely commit the  money expressed as a cash flow) and this is the
                 project to conditions which may constrain    basis of mineral project evaluation. Another
                 scope and compromise value.                  aspect of value is its use in a relative sense,
                   Sufficient sample collection and test work  that is the ranking of a group of similar pro-
                 has taken place during a feasibility study for  jects, or options within one project (King 2000).
                 more of the resource estimate to be reported in  This relative value is based upon ranking
                 the measured category. On large projects sev-  each project’s absolute value and is particularly
                 eral million dollars may have been spent to  useful when a company has several projects
                 bring the project to feasibility study level. Sen-  competing for funds. Any company has finite
                 sitivity analyses will have been run to assess  managerial and financial resources and a
   277   278   279   280   281   282   283   284   285   286   287