Page 308 - Introduction to Mineral Exploration
P. 308

12: CLIFFE HILL QUARRY AGGREGATE RESERVES  291


                 TABLE 12.1 Some major Phase 3
                 costs.                        cost center                             Order of magnitude
                                                                                       of expenditure in
                                                                                       1987–88 £ values
                                               1 Exploration drilling to end of 1986   280,000
                                               2 Sample testing to the same date        25,000
                                               3 Geological and geophysical surveys     80,000
                                               4 Landscape design work                  75,000
                                               5 Engineering design work and research  100,000
                                               6 Financial and administrative           75,000
                                                 considerations
                                               7 Compilation and submission of          20,000
                                                 planning application
                                               Approximate total of major costs        655,000




                 some suitable connection, for processing at  vast scales envisaged are prohibited in the UK.
                 Stud Farm.                                   Such reports must be with the Inspectorate
                   Once planning permission had been granted,  at least 30 days before the commencement of
                 Tarmac undertook a full financial feasibility  the operations to which they relate. The quarry
                 study, after which further applications were  development as a whole will necessitate the
                 submitted in 1986, both to permit an accelera-  excavation of several million cubic meters of
                 tion of the development of the new quarry, and  overburden (down to a depth of 40 m) and the
                 for the construction of a direct rail link from  disposal of this material into natural-looking
                 the site to the Leicester to Burton railway line  landforms on the surrounding lands.
                 (Fig. 12.2). Both proposals received planning  The major operations constituting Phase 4
                 consent in the same year. Numerous controls  of the development were: further drilling and
                 and legally binding agreements are associated  testing, overburden removal, landform crea-
                 with the planning consents, and were formul-  tion, detailed site investigation for foundation
                 ated in discussions between the planning au-  design for the plant site (Barrett 1992), plant
                 thority and the company prior to the consents  site excavation, quarry development, blasting,
                 being granted.                               road and rail access construction, the cultiva-
                   An approximate estimate of some of the ma-  tion and restoration of the completed over-
                 jor costs for Phase 3 (as defined above) under a  burden disposal areas, and the erection of the
                 number of headings are tabulated in Table 12.1.  plants and ancillary structures. A brief sum-
                                                              mary of the Phase 4 progress on an annual basis
                                                              is as follows.
                 12.5  PHASE 4  – DETAILED ENGINEERING          In 1986 earthworks commenced at the new
                                                              site, with the clearing of hedges, the lifting and
                 The Phase 3 drilling, testing, and other evalua-  storage of topsoil from approximately half the
                                                                                                   6
                 tion exercises having proved, to an acceptable  site, and the excavation of around 1.6 × 10 m 3
                 risk level, the existence of an economically  of overburden, mainly from the proposed plant
                 viable quality and quantity of material, the  site at the western extremity. The excavated
                 major cost operations (collectively designated  material was used to create a new landform
                 as Phase 4) commenced in 1986.               on the southwestern perimeter of the site
                   In anticipation of the commencement of     (Fig. 12.8). Two electricity powerlines were
                 major operations, extensive site investigation  also re-routed during this period.
                 surveys were carried out to provide the data   In 1987 earthworks continued with the
                                                                                        6
                                                                                           3
                 for the compilation of the statutory Mines &  stripping of a further 1.6 × 10 m  of overbur-
                 Quarries (Tips) Regulation 9 reports, without  den. This operation exposed bedrock over a
                 which bulk excavations and depositions on the  workable area and completed the excavation of
   303   304   305   306   307   308   309   310   311   312   313