Page 309 - Introduction to Mineral Exploration
P. 309

292   M.K.G. WHATELEY & W.L. BARRETT



                                                                            TABLE 12.2  Some major Phase 4
                  Cost center                             Order of magnitude  costs.
                                                          of expenditure in
                                                          1988–89 £ values
                  1 Overburden excavation and disposal    15,000,000
                  2 Post Phase 3 drilling and testing       192,000
                  3 Landscaping design, cultivation,        375,000
                    supervision
                  4 Plant purchase, erection,             30,000,000
                    commissioning
                  5 Road improvements and rail link        3000,000
                  6 Quarry development and sundry          4000,000
                    other costs
                  Approximate total of major costs        52,567,000


                  the plant area. The overburden was disposed of  1990 saw most of the planned works
                  along the southwestern perimeter to complete  completed and several million tonnes of rock
                  this new landform. Some 8 ha of new landform  produced. In the future further scheduled over-
                  were cultivated and seeded, and rock removal  burden removal and bank building phases will
                  to form the primary crusher slot and platform  be required, and are incorporated with appro-
                  commenced. Highway improvements were        priate safeguards in the planning consents.
                  undertaken, and erection of the plant and asso-  Phase 4 costs are shown in Table 12.2.
                  ciated infrastructure commenced towards
                  the year’s end.
                    During 1988 the erection of the processing  12.6  QUARRYING AND ENVIRONMENTAL
                  plant, the asphalt and ready mixed concrete      IMPACT
                  plants, the electrical substations, weigh-
                  bridges, and offices was started and continued  The Stud Farm (now known as New Cliffe Hill)
                  throughout the year. The development of     quarry is nearing the end of its life with annual
                  quarry benches and further overburden strip-  production of 4.5 Mt of crushed aggregate, and
                  ping was also carried out in 1988. The overbur-  extraction will probably be complete in 2005.
                  den was deposited to create a new landform  As envisaged in the original plan, production
                  along the northern and western perimeter    will then move back to Old Cliffe Hill with
                  of the site. All completed landform sections  processing at the New Cliffe Hill plant. In order
                  were cultivated and seeded and tree planting  to accomplish this, the two quarries have been
                  commenced around the main entrance to the   linked by a 725-m-long, 9 × 6 m tunnel. This
                  quarry.                                     should enable production to continue until at
                    In 1989 the erection of the plants and ancil-  least 2024, subject to a review by the planning
                  lary structures was essentially completed and  authorities in 2007. The Cliffe Hill quarries are
                  plant commissioning commenced towards the   run by Midland Quarry Products, a joint ven-
                  end of the year. Further quarry development  ture of Tarmac with Hanson Quarry Products,
                  was carried out to create the approximately  formed in 1996 to enable more efficient work-
                  200 m of 15-m-high faces that will be needed to  ing of their reserves in the area.
                  sustain the anticipated production. The rail  The Cliffe Hill quarries are a long-term op-
                  link was also completed and officially opened  eration and have had to adapt to the changing
                  in October (Figs 12.2 & 12.8).              public attitudes and social makeup of the local
                    Cultivation and planting works continued  population. During much of the twentieth cen-
                  on the completed landforms and the Central  tury the impact of quarrying was overshad-
                  Electricity Generating Board commenced the  owed by that of deep level coal mining in the
                  erection of new pylons to enable the 132 kV  nearby area. Since the cessation of coal mining
                  powerline to be re-routed in 1990.          in the early 1990s the area has become home to
   304   305   306   307   308   309   310   311   312   313   314