Page 198 - Mathematical Models and Algorithms for Power System Optimization
P. 198

Discrete Optimization for Reactive Power Planning 189

               Results of Case 2 are shown in Tables 6.10 and 6.11. Table 6.10 shows integer solutions of
               the decomposition and coordination algorithm, whereas Table 6.11 shows the integer
               solutions by independent solution method. Similarly, the values in “sum of setting” column in
               Table 6.10 are larger than that in Table 6.11. However, the values in “Y C ” column are smaller
               than that in Table 6.11, that is, installation cost is smaller by decomposition and coordination
               algorithm.
               The results of Case 1 show that results of the algorithm proposed is better than independent
               solution method in the number of newly installed nodes, as well as the number and cost of newly
               installed VAR nodes. The results of Case 2 show that the algorithm proposed obtains a better
               solution in the number and cost of newly installed VAR nodes, even if the same number of
               newly installed VAR nodes is selected.

               To further explain the coordination procedure, Table 6.12 shows the detailed process of total
               infeasibility reduction in the first iteration of Case 1:

               (1) With integer constraint conditions relaxed, each state will be separately solved by LP. On
                    this basis, integer solutions of each state will be rounded off, and the maximum value of
                    integers under each state will be taken as the initial integer solution.
               (2) Under initial integer constraint, MILP algorithm in Section 6.3 will be used to solve all
                    states. At the moment, States 2, 4, and 5 are found infeasible, leading to a total infeasibility
                    of 0.336.
               (3) Coordinate each state: Calculate the infeasibility q ij of each infeasible state, then calculate
                    total infeasibility q j . According to q j , node 75 is the node that can minimize the infeasible
                    q ij ; set new VAR unit at the node; repeat the previous procedure, until all states are
                    feasible, that is, total infeasibility is 0.
               (4) Improvement of integer solution: Select a pair of nonzero integers, and add one of the
                    integers by 1 and reduce another by 1, so as to reduce the fixed costs (Table 6.13).




                               Table 6.8 Results of Case 1 by coordinated solution method
                                                     Node No.
                                                                                            Sum of
                State    74     75    82     95     97     99    101    102    106    123   Setting

                1                                    1                   6      2             9
                2               2      1      7      2      1     7      7                   27
                3                             7                          2                    9
                4        1      2      1      2      2      1     7      7      1      1     25
                5        1      2      1      1      2      3     1      1      2      2     16
                         1      2      1      7      2      3     1      7      2      2     28
                Y C
   193   194   195   196   197   198   199   200   201   202   203