Page 197 - Mathematical Models and Algorithms for Power System Optimization
P. 197

188 Chapter 6

            transmission lines are double-circuit lines. System design normally shall meet N 1 condition,
            however, outage states considered in this section consist of double outages of line and
            generator, that is, meeting N 2 condition.

            As a preliminary test, two cases are used in calculation, where the double outages on a
            single-circuit and a generator are selected as contingency conditions. Table 6.6 shows Case 1
            with five double outages, and Table 6.7 shows Case 2 with seven double outages. CPU
            calculation time of Case 1 is approximately 3min, and Case 2 is about 5min. For planning
            problems, the calculation time is acceptable.


                                       Table 6.6 Outage states of Case 1
                      State Number               Outage Line        Outage Generator
                      1                           104–110               Node 27
                      2                            95–96                Node 31
                      3                            96–102               Node 22
                      4                            75–76                Node 36
                      5                            71–75                Node 37



                                       Table 6.7 Outage states of Case 2
                      State Number               Outage Line        Outage Generator

                      1                           104–110               Node 27
                      2                            95–96                Node 31
                      3                            96–102               Node 22
                      4                            75–76                Node 36
                      5                            71–75                Node 37
                      6                           104–110               Node 25
                      7                           102–103               Node 25

            For comparison, the two cases are solved independently and coordinately, and the results are
            shown in Tables 6.8–6.11, respectively. A row labeled “Y C ” in the table indicates the maximum
            number of VAR units at the node; a column labeled "Sum of units" indicates the total number of
            units in each state.

            Results of Case 1 are listed in Tables 6.8 and 6.9. Table 6.8 shows integer solutions of the
            decomposition and coordination algorithm. Table 6.9 lists integer solutions obtained with
            independent solution method. The values in “sum of setting” column of Table 6.8 are larger
            than that in Table 6.9. However, the values in “Y C ” column are smaller than that in Table 6.9.
            These tables show that the installation cost obtained by decomposition and coordination
            algorithm is less than that by independent solution method.
   192   193   194   195   196   197   198   199   200   201   202