Page 168 - Numerical Analysis and Modelling in Geomechanics
P. 168

MODELLING OF GROUND WAVES 149
              The  impact  of  the  hammer  onto  the  pile  head  was  modelled  with  the
            conceptual model, and various values for the parameters , and were considered.
            The  closest  match  with  site  pile  head  records  was  achieved  with  and  Typical
            ranges of values for the parameters are and The values for stiffness of the dolly
            and mass of the anvil are slightly outside these bands because of the special pile
            cap required for the SIMBAT tests.
              The correlation between field measured and computed pile head displacement-
            time  and  force-time  functions  was  quite  close  in  magnitudes,  but  the  force
            duration was overestimated, Figure 5.13.
              In stage 2 the force-time function was imposed onto the head of the model of
            pile  shaft  plus  springs  and  dampers.  The  displacement-time  functions  were
            computed at each of the spring and damper sets on the shaft and toe.
              In stage 3, the displacement-time functions were imposed onto the shaft and
            toe interface nodes of the FE/IE mesh. The computed surface vibrations at 5.5 m,
            10m  and  16.5  m  from  the  pile  are  compared  with  measured  values  in  Figures
            5.14 and 5.15.
              Some discrepancies are apparent in the radial values, with measured S-waves
            generally larger than those computed. Also, there appears to be an observed early
            P-wave  component,  probably  due  to  an  eccentric  strike,  and  a  later  hammer
            bounce trace. However, close agreement is shown in the vertical waves. Overall,
            however,  the  agreement  is  encouraging,  considering  the  ground  variability  and
            the imperfect impacts.


                            Impact driving at Flitwick, Bedfordshire
            A  second  calibration  exercise  is  now  presented,  for  the  driving  of  a  12m  long
            steel H-pile (305×305×89 kg/m), using a 3200 kg drop hammer falling through 1.
            0 m. The soil conditions comprised topsoil and soft clays to 2.4 m, loose sand
            and gravel at 2.4–4.8 m, then very dense uniform sands to considerable depth.
            The  water  table  (WT)  was  at  2.4  m.  Although  the  static  elastic  moduli  for  the
            three layers were estimated to be 5 MPa, 20 MPa and 50 MPa respectively, the
            dynamic stiffnesses used for the stage 3 computation were identified as 20 MPa
            above the WT and 200 MPa below. The three-stage computation was conducted
            for the condition of 7 m penetration depth.
              A  summary  of  some  of  the  parameters  used  in  the  analyses  of  the  hammer
            impact, the pile shaft and the pile toe is given in Table 5.2.
              Although  no  pile  head  signals  were  available  during  driving,  the  ground
            surface vibrations were recorded, and comparisons with the computed values are
            shown in Figure 5.16, for radial particle velocities at 7 m and 16.5 m distances
            from the pile. The observed signals appear to include an extra peak from an early
            P-wave arrival, which is accentuated at 16.5 m, and was probably caused by an
            eccentric strike. Otherwise close correlation is achieved.
   163   164   165   166   167   168   169   170   171   172   173