Page 60 - Numerical Analysis and Modelling in Geomechanics
P. 60

COMPRESSED AIR TUNNELLING 41
            50 m of the tunnel length was constructed using a twin sidewall drift method (see
            Figure  2.6a).  From  50  m  to  320  m,  the  tunnel  was  constructed  by  a  single
            sidewall drift method (see Figure 2.6b) and from 400 m to 635 m, the tunnel was
            converted to twin tunnels (see Figure 2.6c).
              Table  2.3  shows  the  change  in  the  tunnel  face  area  with  tunnel  advance  for
            each  heading  together  with  the  method  of  construction.  Table  2.4  shows  the
            perimeter area (per unit length of the tunnel) and the thickness of the initial and
            final layer of shotcrete.
              Figure 2.7 is a geological section of the tunnel route. The soil layers comprise
            a coarse gravel layer near to the ground surface underlaid by sand. Beneath the
            sand is a layer of low permeability silty clay underneath which lies another layer
            of sand. Also, there is a lens of sand in the silty clay layer between chainages 300
            m  and  635  m.  The  groundwater  level  is  approximately  5  metres  below  the
            ground surface.

















            Figure 2.6 Method of construction.





















            Figure 2.7 Geology of the tunnel route.
   55   56   57   58   59   60   61   62   63   64   65