Page 340 - Orlicky's Material Requirements Planning
P. 340

CHAPTER 19   Repetitive Manufacturing Application                               319


        ed or stopped until the supplier is able to provide the needed part. There is insufficient
        response time for the supplier to react to a requirement that blindsides him or her. If a
        supplier has been delivering blue parts at a constant rate and then, all of a sudden, a kan-
        ban shows up with a demand for a striped part, the chance that the striped part will be
        available is very small without having some forewarning that the demand is coming.
        This is why an MRP system still has an integral place in a repetitive manufacturing busi-
        ness. MRP can very effectively plan to the day exactly what is required and when.
        Practically speaking, most facilities find a daily schedule to be sufficient to support pro-
        duction. Rarely can an enterprise schedule and react to the hour or exact time. The kan-
        ban then can become the execution tool of less than one day’s duration with the exact tim-
        ing of the replenishment when production is ready.


        RATE-BASED SCHEDULING
        Rate-based scheduling occurs when a production schedule is entered directly into the
        system as a date range with volumes. The following could be an example of a rate-based
        schedule:

             Product 135948                           Production per Day
             June 10–August 15                                     12,000
             August 16–September 22                                15,000
             September 23–October 31                               20,000
             November 1–November 30                                30,000
             December 1–March 30                                   20,000
             March 31–June 9                                       10,000
             The rate-based schedule also can be entered as rate per shift if that level of control
        is desired. This higher level of detail is required to plan the staffing for each shift. The
        increased visibility prevents surprises and allows shop supervisors to adjust the affected
        resources to match the desired production rate.

           Production Schedule
           Product 135948              Shift 1        Shift 2       Shift 3

           June 10–August 15            6,000          3,000         3,000
           August 16–September 22      10,000          3,000         2,000
           September 23–October 31     10,000          5,000         5,000
           November 1–November 30      10,000         10,000        10,000
           December 1–March 30         10,000         10,000            0
           March 31–June 9             10,000             0             0

             This example provides the necessary visibility required to identify when additional
        shifts are required. Since there is usually a premium paid to the off-shifts, the strategy
   335   336   337   338   339   340   341   342   343   344   345