Page 416 - Orlicky's Material Requirements Planning
P. 416

CHAPTER 23   Strategic Inventory Positioning                                    395


           FIGURE 23-5
                                      Longest Lead Time Path = 8 Days
           Realistic lead
           time for Part 101.                      2   101


                                5   201                203     6   204




                                    301           302      303P   304P



                                401P    402   403P   404P



                                       501P



           FIGURE 23-6
                                                      2  101
           BOM with ASR
           lead time
           stratifications.
                                  5   201             7  203         204   6



                                  4   301        4   302      303P   304P

                                                                     3
                               3  401P    402    403P   404P

                                     4                  3
                                         501P



        ASRLT of 14 days. Part 301 has an ASRLT of 8 days. There are three independent ASRLT
        groups within the Part 101 BOM.
             ASRLT is a qualified CLT. By using the ASRLT approach, planners now can calcu-
        late and/or determine more realistic dates for the replenishment or delivery of a part. Of
        course, using this approach requires each discrete part number to have an MLT or pro-
        duction lead time (PLT), and those lead times should be as accurate as possible. ASRLT
        is a pivotal building block for where to position inventory, the size of those inventory
        positions, and critical date-driven alerts and priorities.