Page 453 - Pipeline Pigging Technology
P. 453

Pipeline  Pigging  Technology


        IDENTIFYING PIPELINE               INTEGRITY        PROJECTS


        The economic risk assessment essentially provides a ranking of pipeline
     segments according to the potential effect of a failure on our business: the first
     step  in  reaching  our  primary goal. The  next  step  is  to  develop  pipeline
     integrity projects that will reduce the economic risk by lowering the probabil-
     ity  of  failures  caused  by  deterioration  of  structural integrity. Some of  the
     guidelines for approval of projects in the programme are:

           1. Projects  to  prevent  outages  on  pipelines with  a known integrity
              problem  that would  otherwise  cause  recurring  failures  must  be
              included in the programme.
           2. Priority for action is indicated by first addressing unacceptable  safety
              risks and then by the ranking of economic risk.
           3. Cost of an individual project ^ 50%  of the  estimated outage conse-
              quences.
           4. Annual programme cost should be approximately 1-2% of operating
              and maintenance costs.

        Fig.9 provides a summary of the projects either completed  in, or planned
     for,  the  years  1988  to  1990 inclusive.  It  is  noteworthy  that  55% of  the
     programme expenditures   have been  on projects to assess the  condition of
     pipelines  anticipated  to have developing  structural integrity problems but
     with no history of failures or observed damage. 72% of the total  expenditure
     was aimed at reducing the risks associated with external  corrosion.

        External corrosion projects


        At the present time, external corrosion is the largest component  (approxi-
     mately 80%) of the estimated outage probability for pipelines with the highest
     estimated economic risk. The two pipelines with known external  corrosion
     (Table 2) were, or will be, re-inspected using an "advanced" in-line inspection
     (ILI) system. The approach of using in-line inspection  and analysis in prefer-
     ence to hydrostatic  testing,  as described in an earlier paper[5], has proven
     satisfactory and is continuing.
        The three pipelines with anticipated  problems were identified solely on
     the basis of the estimated risk. "Conventional" ILI systems were used on two
     of the lines and an "advance" ILI system was used on the other line. External
     corrosion of varying severity and extent was found on each of these pipelines



                                       434
   448   449   450   451   452   453   454   455   456   457   458