Page 457 - Pipeline Pigging Technology
P. 457

Pipeline  Pigging  Technology


        DISCUSSION


        The risk-assessment methodology that is the basis for our pipeline integrity
     programme has resulted in continued focus of our efforts to reduce  the risks
     of  failures  caused  by  external  corrosion.  The  resulting pipeline-integrity
     projects  involve in-line  inspection  of pipelines which  have very high  eco-
     nomic consequences  of an outage, or very large numbers of known corrosion
     damage areas. Both these situations place a premium on the ability of in-line
     inspection  to  provide  data  that  allows  failure  pressures  to  be  estimated
     without excavations to determine the  size of corrosion  damage.
        When   excavating  locations  to  investigate  external  corrosion  or  stress
     corrosion  cracking, it is NOVA's policy to reduce the pressure to 70% of the
     recent operating pressure to protect the safety of workers. Even with advance
     planning,  such  pressure  reductions  can  affect  border  deliveries under  the
     current  situation with the system operating so close to capacity throughout
     the year. In the  case of one project  to assess anticipated corrosion  on a line
     with moderate outage probability but very high outage consequences,  such
     pressure  reductions would  have resulted  in reduced  gas exports valued at
     over $ 1 million per day if any other operating disruptions occurred. As a result,
     an "advanced" ILI system, whose performance has been established[8], was
     used on this line, rather than a lower-cost conventional system, in order  to
     avoid the excavations that would have been otherwise required to assess the
     significance  of detected  corrosion  damage.  Even  so,  the  reduction  in  gas
     volumes required  for in-line inspection  is a disruption  to system  operation.
     We  are  examining methods  of including such  business  effects  in  the  cost
     estimates of pipeline integrity projects,  to make sure that the cure  (pipeline
     integrity project)  is not worse that the disease (an unplanned outage due to
     a  failure). We are  also encouraging  the  vendors  of  inspection  services  to
     develop methods that will allow their equipment to perform in high-velocity
     gas streams, so that we can refer to it as "on-line" inspection, rather than "in-
     line", which it truly is at present.




        CONCLUSIONS


        1. NOVA's pipeline-integrity programme has allowed us to determine what
     testing and inspection programmes are appropriate  to our system.
        2.  With  a  total  cost  of  2% of  operation  and  maintenance  costs,  the
     programme   is affordable.


                                       438
   452   453   454   455   456   457   458   459   460   461   462