Page 102 - Pipeline Risk Management Manual Ideas, Techniques, and Resources
P. 102

4/80 Corrosion Index
           rectifiers and bonds must be maintained. Inspections of these   surveys where  readings  are taken  at  short  intervals such as
           pieces of equipment are usually performed at shorter intervals   every 3 to 15 feet.
           than the overall check of the potential levels. Because a rectifier   An annual test lead survey is the cornerstone of many opera-
           provides the driving force for the cathodic protection systems,   tors’ CP verification  programs. A  pipe-to-soil  measurement
           the operator must not allow a rectifier to be out of service for   taken  at  a  test  lead  measurement  indicates  the  degree  of
           any  length  of  time. Monthly  or  at  least bimonthly  rectifier   cathodic protection  on the pipe because it  indicates the ten-
           inspections are often the norm.            dency of current flow, both in terms ofmagnitude and direction
             Use of  a risk  assessment  adjustment  factor  that  could  be   (to the pipe  or from the pipe) (see Figure 4.6). Uncertainty
           called something like a rectifier interruption factor is one way   increases with increasing distance from the test lead because
           to account for the effects of inconsistent application of CP. An   the test lead reading represents the pipe-to-soil potential in only
           interruption or outage can be defined as some deviation from   a localized area. Because galvanic corrosion can be a localized
           normal rectifier output (probably in amperes) once sufficient   phenomenon,  the test leads provide only limited information
           data have been accumulated to establish a baseline or normal   regarding CP levels distant from the test leads. A test lead read-
           output for a rectifier. The tracking of kilowatt-hours may also   ing is therefore an indicator of cathodic protection only in the
           be useful in determining outage periods. The hours of outage   immediate  area  around  the  lead-a   lateral  distance  along
           per year can be tracked and accumulated to assign risk assess-   the pipe that is roughly equal to the depth of cover, according to
           ment penalties for both high outage hours in any year and the   one rule of thumb. Closer test lead spacings, therefore, yield
           accumulation of outage hours over  several years. Each indi-   more information and less chance oflarge areas of active corro-
           cates periods during which the pipeline might not be adequately   sion going undetected. Because corrosion is a time-dependent
           protected from corrosion.                  process, the number oftimes the test leads are monitored is also
             A potential difficulty in application of such rectifier  inter-   important.
           ruption factors is that each rectifier must be linked to the spe-   Using these concepts, a coarse point schedule can be devel-
           cific pipeline lengths that are influenced by that rectifier. The   oped based on general criteria such as:
           adjustment factor is derived from each rectifier, but the penalty
           applies to the actual portions of the pipeline that suffered the   All buried metal  in the vicinity of the pipeline  is monitored
           inconsistent application of CP In a complex system of recti-   directly by test leads, and test lead spacing is no greater than
           fiers  and  pipelines,  it  is  often  difficult  to  ascertain  which   1 mile throughout this section  Best
           rectifiers are influencing which portions of pipeline.   Test leads are spaced at distances of 1 to 2 miles apart (maxi-
             Tracking the equipment performance might also provide the   mum) and all foreign pipeline crossings are monitored via
           ability  to better  quantify  the benefits of remote  monitoring   test leads; not all casings are monitored; there may be other
           capabilities. If a system is installed to monitor and alarm (in a   buried metal that is not monitored  Fair
           control center as part of the SCADA system, perhaps) rectifier   Test lead spacing is sometimes more than 2 miles; not all poten-
           malfunctions  and  perhaps  even pipe-to-soil  readings  at  test   tial interference sources are monitored  Poor
           leads, then outage times and inadequate protection times can be
           minimized.  Depending  on the corrosion  rates and economic   A more robust assessment can use actual distances from the
           considerations such as labor costs and availability, adding such   nearest test lead to characterize each point along the pipeline.
           monitoring capabilities might be justified.   This would penalize (show higher risks), on a graduated scale,
                                                      those portions of the pipeline that are farther away from a test
           Test leads   Often,  the primary  method  for  monitoring the   lead or other opportunity for a pipe-to-soil potential reading.
           effectiveness of a cathodic protection system is through the use   The frequency of readings at test leads is rated as follows.
           of test leads, fixed survey points for taking pipe-to-soil voltage   Pipe-to-soil readings are taken with the IR drop understood and
           readings.  A  test  lead  is  normally  a  wire  attached  (usually   compensated at intervals of
           welded  or  soldered)  to  the  buried  pipeline  and  extended
           above the ground. A test lead allows a worker to attach a volt-   <6 months   Best
           meter with a reference electrode and measure the pipe-to-soil   6 months-annually   Fair
           potential.                                 >annually                          Poor
             Placement  of test  leads  at  locations where  interference  is
           possible is especially important. The most common points are   Notes: As previously explained, lack of proper IR drop com-
           metal  pipe  casings  and  foreign  pipeline  crossings.  At these   pensation  may  negate the effectiveness of  readings. For our
           sites, careful attention should be paid to the direction of current   purposes here, test lead can be any place on the pipeline where
           flow to ensure that the pipeline is not anodic to the other metal.   an accurate pipe-to-soil potential  reading  can be taken. This
           Where pipelines cross, test leads on both lines can show if the   may  include most  aboveground  facilities,  depending  on  the
           cathodic protection systems are competing.   type of coating present.
                                                        Readings taken at longer intervals such as greater than one
           survevs   Several survey types are commonly used to verify   year do have some value, but a year’s worth of corrosion might
           that effectiveness criteria are being met. These include varia-   have proceeded undetected between readings.
           tions in how pipe-to-soil readings are taken and where they are
           taken. Examples of the former include on readings, instant-off   Close interval  surve-vs   A  powerful  tool  in  the  corrosion
           readings, voltage gradient, and polarization measurements as   engineer’s tool bag is a variation on test lead monitoring called
           previously described. Variations in where readings  are taken   close intenialsurveying (CIS) or closespacedsurveying. In this
           include readings at test lead stations only versus close interval   technique, pipe-to-soil readings are taken (and IR compensa-
   97   98   99   100   101   102   103   104   105   106   107