Page 343 - Pipeline Risk Management Manual Ideas, Techniques, and Resources
P. 343

14/320 Absolute Risk Estimates
            that would better refine these estimates have been available. It is also   Since the national pipeline system is not characterized in these terms,
            important to note that frequencies and probabilities like these repre-   the similarities cannot be confirmed. However, since the LMP speci-
            sent averages expected only over long periods oftime. Short time peri-   fies several state-of-the-art spill size reduction measures not typically
            ods  can  have  different  experience  and  still  be  appropriately   seen in other pipelines, it is reasonable to assume that the national data
            represented by these frequencies. Therefore, the predictive power of   will not underestimate the spill size potential and very probably will
            these probabilities is limited.            overestimate the potential.
              As an additional evaluation step, the plausibility of the estimated
            post-mitigation  leak  frequency  was  examined  qualitatively. The   A second assumption is that the <50 bbl spill size fraction seen
            estimate is generally supported by this qualitative analysis. summa-   under EPC operations is representative of LPP’s future spill size dis-
            rized as follows:                          tribution. Since the <50 bbl size triggers few impacts and since >50
                                                       bbl spill fraction can be  separated from the “all size” distribution,
             1.  Low leak frequencies over long periods oftime are being experi-   the  absolute  validity  of  this  assumption  is  not  critical  to  thls
              enced by  US pipeline operators on hazardous liquid pipeline of   analysis.
              similar length to the LPP pipeline, but without the extraordinary   An additional underlying assumption in these estimates is that the
              level of mitigations as proposed in the LMP. This is indicated by   relative probability of failure remains fairly constant over the life of
              informal  interviews  with pipeline  operators  and with searches   the project. This is accomplished by  LPP reacting appropriately to
              and analyses of OPS accident data. Analyses of these latter data   changing conditions along the line, as is specified in the LMP. It also
              are  discussed  in  Attachment  E  [not  included  in  this  book].   requires that the integnty verifications as scheduled by ORA calcula-
              Results  of summary analyses  of DOT and other data are pro-   tions, ensure that the probability of failure does not exceed the pro-
              vided. These data and analyses  suggest that the estimated  leak   jected  leak  probabilities  between  integrity  verifications.  This  is
              frequency is possible, especially with increased mitigation.   discussed in Appendix 9D [not included in this book].
            2.  The  correlation  as described  in Attachment A  [see page  2981,
              although weak  in terms of statistically valid data quantity and
              quality, nonetheless offers a semi-quantitative linkage that sup-   Description ofpotential impacts
              ports the estimate.
             3.  Appendix T [not included in this book] shows leak rate estimates   Nine distinct potential impacts are studied in this report. Impacts are
                                                       site-specific and sensitive to many variables, and therefore must be
              for approximately 60 U.S. hydrocarbon liquid pipeline operators.   somewhat generalized to present a risk picture of the entire line. For
              These leak rates, presumably achieved under typical industry miti-   modeling  purposes,  the  frequency  of  each  impact  is  potentially
              gation levels, show the range of different leak rates that are possi-   affected by variables  of.
              ble. This includes company-wide leak rates that are approaching
              the estimated post-mitigation leak frequency estimates forthe LPP
              pipeline.                                  Index sum-representing  the probability of pipeline failure;
             4.  The  scenario-based  analyses  detailed  in  Attachment  B  [this   Spill size; and
              excerpt can be found in Chapter 3, see pages 00001 suggests that   Tier designation-representing  receptor vulnerability and sensitiv-
              the  estimated leak rate reductions can be  achieved with  rather   ity (e.g., Tier 3 is hypersensitive).
              modest assumptions regarding mitigation effectiveness, even for
              the more problematic challenge of reducing third-party damage.   However, not all impacts are modeled as being sensitive to all ofthese,
             5.  An alternative approach to estimating failure probabilities from   due to data availability limitations. Below is a general description of
              several common pipeline failure mechanisms has produced very   the impacts modeled. These descriptions offer the reader a general
              similar results. This alternative approach, shown in the preliminary   sense of the rationale behind the calculation, but note that the actual
              ORA [ORA = Operational Reliability Assessment, not included in   results are based on more than a hundred calculated scenarios. More
              this book] uses concepts from fracture mechanics, materials sci-   detailed descriptions can be found in Attachment C [Appendix F of
              ence, historical data. and statistics to calculate failure rates and   this book].
              probabilities. The fact that two separate approaches to failure prob-
              ability estimation arrived at similar conclusions provides support   Fatalities and injuries
              for both calculations.
             6.  In the experience ofthe EA authors, the LMP reflects levels ofmit-   While it is common to express risks of injuries and fatalities as a
              igation  unprecedented  in  the  industry. This suggests that high   function of “hours exposed,” this analysis uses only a calculation of
              levels of leak rate reductions are possible, even if not commonly   fatalities  and injuries per reportable  leak. All distinctions of rural
              observed.                                 versus urban; permanent residents versus temporary exposures; dis-
             In addition to overall leak frequencies, spill size frequency also plays a   tances to leaks; ignition probabilities; etc. are therefore aggregated in
             role inmany ofthe impacts.Aspill sizedistributionforspillslargerthan   these  ratios.  This  implies  that  the  LPP  system  is  similar  to the
             50 bbl  was  derived  from  DOT hazardous liquid pipeline reportable   national data in terms of these variables. The national pipeline sys-
             spills from 1975 to early 2000. The fraction of spills smallerthan 50 bbl   tem is not characterized to the extent that such similarities can be
             was estimated from the 29 year EPC leak experience on the 450 mile   confirmed. However, no compelling reasons  are found to suggest
             segment fromValve  J- 1 to Crane. EPC leak experience contains too few   that LPP is not  similar, with regards to the distinctions previously
             larger-sized spills to create a meaningful profile.   noted. Therefore, for the purposes of the overall impact estimations,
                                                        the national  data (DOT) is assumed to be representative of LPP’s
              Embedded in this approach is the assumption that the national spill   future risks for this impact.
             size distribution (DOT data) is representative of the LPP’s future spill
                                                         An example of fatalities and injuries, is Case 1 shown in Table 3. It
             size distribution. This implies that the following variables are also   can be described in general terms as follows:
             representative:
                                                         Statistically,  one  fatality  is  expected  to  occur  for  every  217
                                                        reportable  leaks  and  an  injury  is  expected to  occur  for  every 48
              Topography;                               reportable leaks.
              Failure mechanisms that determine hole size;   The industry average leak rate applied to this pipeline results in an
              Leak detection capabilities; and          estimate of 35 leaks over 50 years and, hence predicted fatalities and
              Leak reaction capabilities.               injuries of 0.16 and 0.72, respectively.
   338   339   340   341   342   343   344   345   346   347   348