Page 69 - Pipeline Risk Management Manual Ideas, Techniques, and Resources
P. 69

3/48 Third-party Damage Index
          Example 3.1: Scoring the depth of cover     tion and pipe coatings, if not the pipe itself. Birds and other
                                                      smaller animals and even insects can also cause damage by
             In this example, apipeline section has burial depths of 10 and   their normal activities. Again, coatings and instrumentation of
             30 in. In the shallowest portions, a concrete slab has been   aboveground facilities are usually most threatened. Where such
             placed over and along the length of the line. The 4-in. slab is 3   activity  presents  a  threat  of  external  force  damage  to  the
             ft  wide  and reinforced  with  steel mesh.  Using the above   pipeline,  it can be assessed  as a contributor to activity level
             schedule, the evaluator calculates points for the shallow sec-   here.
             tions with additional protection and for the sections buried   The activity level item is normally a risk variable that may
             with 30 in. of cover. For the shallow case: IO in. of cover + 24   change over time, but is relatively unchangeable by the pipeline
             in. of additional (equivalent) cover due to slab = (10 + 24)/3   operator. Relocation is usually the only means for the pipeline
             pts = 11.3 pts. Second case: 30 in. of cover = 30/3 = IO pts.   operator to change this variable, and relocation is not normally
             Because  the  minimum  cover  (including  extra protection)   a routine risk mitigation option.
             yields the higher point value, the evaluator uses the  IO-pt   The evaluator can create several classifications  of activity
             score for the pipe buried with 30 in. of cover as the worst case   levels for risk scoring purposes.  She does this by describing
             and, hence, the governing point value for this section.   sufficient conditions such that an area falls into one of her clas-
              A better solution to this example would be to separate the   sifications. The following example provides a sample of some
             10-inch and 30-inch portions into separate pipeline sections   of the conditions that may be appropriate. Further explanation
             for independent assessment.              follows the example classifications.
             In this section, a submerged line lies unburied on a river bot-
             tom, 30 ft below the surface at the river midpoint, rising to   High activity level (0 points)   This area is characterized by
             the water surface at shore. At the shoreline, the line is buried   one or more of the following:
             with 36 in. of cover. The line has 4 in. of concrete coating
             around it throughout the entire section.   Class 3 population density (as defined by  DOT CFR49Part
                                                       192)
            Points  are assessed  as follows: The shore aonroaches  are   0  High population density as measured by some other scale
                                         II
           very shallow; although boat anchoring is rare, it is possible. No   Frequent construction activities
           protection is offered by water depth, so 0 pts are given here. The   0  High volume of one-call or reconnaissance reports (>2 per
           4 in. of concrete coating yields 5 pts. Because the pipe is not   week)
           buried beneath the river bottom, 0 pts are awarded for cover.   Rail or roadway traffic that poses a threat
                                                       Many other buried utilities nearby
                       Total score =O + 5 + 0 = 5 pts   Frequent damage from wildlife
                                                       Normal anchoring area when offshore
                                                       Frequent dredging near the offshore line.
           B.  Activity level (weighting: 20%)
                                                      Medium activiy level (8 points)   This area is characterized
           Fundamental to any risk assessment is the area ofopportunity.   by one or more of the following:
           For  an  analysis of third-party  damage potential,  the  area  of
           opportunity is strongly affected by the level of activity near the   Class 2 population density (as defined by DOT)
           pipeline. It is intuitively apparent that more digging activity near   Medium population  density nearby, as measured by  some
           the line increases the opportunity for a line strike. Excavation   other scale
           OCCUTS frequently in the United States. The excavation notifica-   No routine construction activities that could pose a threat
           tion system in the state of Illinois recorded more than 100,000   Few one-call or reconnaissance reports (<5 per month)
           calls during the month ofApril 1997. New Jersey’s one-call sys-   Few buried utilities nearby
           tem records 2.2 million excavation markings per year, an aver-   Occasional wildlife damage.
           age of more than 6000 per day [64]. As noted previously, it is
           estimated that gas pipelines are accidentally struck at the rate of   LOW activity level (I5 points)   This area is characterized by
           5 hits per every 1000 one-call notifications.   all of the following:
            DOT accident statistics for gas pipelines indicate that, in the
           1984-1987  period,  35%  of  excavation  damage  accidents   Class 1 population density (as defined hy DOT)
           occurred in Class  1 and 2 locations, as defined hy DOT gas   Rural, low population density  as measured by  some other
           pipeline regulations  [87]. These are the less populated areas.   scale
           This tends to support the hypothesis that a higher population   Virtually no activity reports (<lo per year)
           density means more accident potential.      No routine harmful activities in the area (agricultural activi-
            Other considerations include nearby rail systems and high   ties where the equipment cannot penetrate to within  1 ft of
           volumes  of  nearby  traffic,  especially  where  heavy  vehicles   the pipeline depth are sometimes considered harmless).
           such  as  trucks  or  trains  are prevalent  or  speeds  are  high.
           Aboveground facilities and even buried pipe are at risk because   None (2Opoints)   The maximum point level is awarded when
           an  automobile  or  train  wreck  has  tremendous  destructive-   there is virtually no chance of any digging or other harmful
           energy potential.                          third-party activities near the line.
            In some areas, wildlife damage is common. Heavy animals   The evaluator may assign point values between these cate-
           such as elephants, bison, and cattle can damage instrumenta-   gories, but should make an effort to ensure consistency.
   64   65   66   67   68   69   70   71   72   73   74