Page 90 - Pipeline Rules of Thumb Handbook
P. 90

Construction  77











































           Figure 2. Rig Side Work Space

           accuracy of the drill profile and alignment is dependent on  diameter for steel line pipe. The curve usually brings the
           the accuracy of the survey information.               profile to the elevation providing the design cover of the
                                                                 pipeline under the river. Long horizontal runs can be made
                                                                 at this elevation before curving up towards the exit point. Exit
                       Profile design parameters                  angle should be kept between 5 and 12 to facilitate handling
                                                                 of the product pipeline during pullback.
             Depth of Cover—Once the crossing profile has been      Drill Survey—Most downhole survey tools are electronic
           taken and the geotechnical investigation complete, a deter-  devices that give a magnetic azimuth (for “right/left” control)
           mination of the depth of cover under the crossing is made.  and inclination (for “up/down” control). Surface locators can
           Factors considered may include flow characteristics of the  also be used in conjunction with the downhole electronic
           river, the depth of scour from periodic flooding, future  package.
           channel widening/deepening, and the existence of existing  Accuracy—The accuracy of the drill profile is largely
           pipeline or cable crossings at the location. It is normally rec-  dependent on variations in the earth’s magnetic field. For
           ommended that the minimum depth of cover be 20ft. under  instance, large steel structures (bridges, pilings, other
           the lowest section of the crossing. While 20ft. is a recom-  pipelines, etc.) and electric power transmission lines affect
           mended depth of cover on a river crossing, crossings of other  magnetic field readings. However, a reasonable drill target at
           obstacles may have differing requirements.            the pilot hole exit location is 10ft. left or right, and -10ft. to
             Penetration Angles and Radius of Curvature—An       +30ft. in length.
           entry angle between 8 and 20 can be used for most crossings.  As-Built Drawings—Normally, survey calculations are
           It is preferable that straight tangent sections are drilled before  conducted every 30ft. during pilot hole operations. As-built
           the introduction of a long radius curve. The radius of the  drawings that are based on these calculations should be pro-
           curve is determined by the bending characteristic of the  vided by the contractor. Alternate methods such as gyroscop-
           product pipeline, increasing with the diameter. A general  ing, ground penetrating radar or “intelligent” pigs may also be
           “rule-of-thumb” for the radius of curvature is 100ft./1-in.  used to determine the as-built position.
   85   86   87   88   89   90   91   92   93   94   95