Page 94 - Pipeline Rules of Thumb Handbook
P. 94

Construction  81

           These pits typically have a volume of at least 500cu.ft.  accepted by the owner. The parties, price and performance
           Depending on the nature of the project, the slurry is pumped  must be specified. Define the project to be undertaken by
           from the return pits to a “settling and containment pit.” These  detailing the scope of work and incorporate all plans and spec-
           pits vary in size depending on pumping rates and contain the  ifications from the bid package.
           slurry for recycling or disposal.
             Recycling Slurry—Slurry that has been circulated down-
           hole and collected in the containment pit is then passed       Differing ground conditions and
           through machinery that separate the cuttings from the slurry.        walkaway provision
           This process involves a series of shaking sieves and various
           size hydroclones.                                       Owners should accept the responsibility of performing an
             Slurry and Cuttings Disposal—Significant amounts of  adequate geotechnical investigation. Despite adequate testing
           slurry are normally disposed of at the end of a project. Eco-  of ground conditions, unknown, unusual, and unexpected
           nomics for disposal is extremely site specific. This slurry can  ground conditions may be encountered. The contract should
           be disposed of by:                                    provide solutions when the project encounters differing
                                                                 ground conditions. The walkaway provision in the contract
             1. Use at another drilling location.
                                                                 should entitle the contractor to stop work and walk away from
             2. Spread onto raw land for water retention improvement.
                                                                 the job without the owner having the right to take over the
             3. Evacuate to a dumpsite.
                                                                 contractor’s equipment. The contractor should be entitled to
           If working in an area of contaminated ground, the slurry  receive compensation for demobilization, lost profits and
           should be tested for contamination and disposed of in a  work performed prior to walkaway. If the project is com-
           manner that meets governmental requirements.          pleted, the contractor should be paid on a cost-plus basis.
                                                                 Assumption of risk of unforeseen ground conditions by the
                                                                 contractor affects the bid price.
                      Cost mitigation for the owner

             With prebid planning and research, the owner can realize         Environmental concerns
           significant savings in slurry disposal. It is in the owner’s inter-
           est to define and specify all disposal issues. In particular:  Before the project begins, address environmental concerns
             1. Define an approved disposal site as part of the project  because owners and contractors are included as potentially
               specifications.                                    responsible parties when environmental damages and
             2. Because it is difficult to estimate disposal quantities, dis-  cleanup costs are assessed. Federal, state and local laws must
               posal should be a separate bid item as either “cost plus”  be evaluated and licensing, permitting and other regulations
               or on “unit rates.”                               must be followed. Directional crossings that damage soil or
             3. Inadvertent returns are not uncommon and difficult to  water may cause liability.
               predict. The issue should be fairly represented to per-
               mitting bodies prior to construction. Contingency plans  1. Turbidity of Water and Inadvertent Returns—As these
               for containment and disposal of inadvertent returns   events are difficult to predict and work stoppage may
               should be priced as a separate bid item and agreed prior  occur, the contract should offer a mechanism to mutu-
               to construction.                                      ally address and mitigate the problem. Liabilities are
                                                                     generally shared by both the contractor and owner and
                                                                     many times can be insured.
                       Conditions of the contract                  2. Slurry Disposal—Comply with the regulations of the
                                                                     area regarding slurry disposal. Slurry disposal should be
             Always utilize a written contract to maximize communica-  referred to in the contract and bid as a separate line item
           tion and minimize controversy. A contract should be used   on a cost plus or unit price basis.
           to anticipate what the parties intend to do if a problem
           occurs on the job. The contract should be readable and
           understandable.                                                    Allocation of risk of loss

                                                                   Evaluate and allocate risks of loss that may occur during
                              Bid package                        the project. Owners should share the risk of loss rather than
                                                                 shifting all the losses through the indemnification to the con-
             A proposal presented by a contractor to the owner is an  tractor because the bid price is directly affected by contin-
           offer by the contractor that becomes a binding contract if  gent losses. Insurance may provide coverage by third parties
   89   90   91   92   93   94   95   96   97   98   99