Page 93 - Pipeline Rules of Thumb Handbook
P. 93

80    Pipeline Rules of Thumb Handbook

              d. External pressure from static head in the drilled hole  Joint Coating—The coating application of the weld area
                and/or overburden pressures must be considered. It  is the most critical field operation to maintain a smooth
                is recommended that the static head resulting from  abrasion-resistant pipe string. It is recommended that the
                the maximum envisaged drilling fluid density should  girth weld be coated with FBE powder utilizing the induc-
                be used with a factor of safety of 1.5 to provide con-  tion heating coil and powder application machine to a
                servative estimations of resulting hoop and longitu-  minimum dry film thickness of 25 mils. As an alternate, two
                dinal stresses.                                component catalyzed liquid epoxy may be applied to the girth
           3. Post-installation                                weld area to a minimum dry film thickness of 25 mils using a
              a. The longitudinal curvature stresses calculated for  paint brush or roller. Tape should never be used for joint
                stage 2.c. above are used again here.          coating on the pullback portion of a directional crossing.
              b. External pressure stresses from 2.d. apply.     Coating Repair—It is recommended that small coating
              c. Hoop and longitudinal stresses resulting from the  damaged areas be repaired with a polymeric melt stick patch-
                final hydrostatic test are calculated.          ing material. Holidays larger than 1in. in diameter should be
           4. In-service                                       repaired utilizing the two component catalyzed liquid epoxy
              a. Curvature—see 2.c.                            applied with a paint brush or roller. Tapes should never be
              b. external pressure—see 2.d.                    used for repair of coating damaged areas on the pullback
                                                               portion of a directional crossing.
           The maximum working pressure of the pipeline is used   Abrasion-Resistant Overcoat—As an extra abrasion-
         in calculating longitudinal and hoop stresses that will be  resistant barrier for crossings that may encounter stones,
         imposed during service.                               boulders or solid rock it is recommended the FBE coated
           Allowable Stresses—Having determined the individual  pipeline be overcoated with an epoxy-based polymer con-
         and combined stresses at each stage of construction and those  crete. The material should be applied at a mill or with a
         for the in-service condition, they must be compared with  portable yard coating machine to a minimum thickness of
         allowable limits.                                     40mils. Girth weld and coating damaged areas should be field
                                                               coated using an epoxy-based polymer concrete compatible
           1. ASME B31.8—1992, Table A842.22 provides the fol-  with the overcoat material. The patch material should be
              lowing limits:                                   applied so the material tapers uniformly and feathers into the
              — Maximum allowable longitudinal stress: 80% SMYS.  original coating. Stability of the pipeline in drilled crossings
              — Maximum allowable hoop stress: 72% SMYS.       is not normally a concern so a Portland cement type concrete
              — Maximum allowable combined stress: 90% SMYS.   coating is not recommended.
              (Where SMYS is the Specified Minimum Yield Strength
              of the pipe material.)
           2. Regulatory bodies may impose additional limits to those  Drilling slurry—containment, recycling
              specified above—owner companies should identify any                  and disposal
              such further constraints and ensure the adequacy of the
              design.                                            The directional crossing process requires the use of large
                                                               volumes of slurry that provide the following functions:

                           Pipeline coating                      1. Hydraulic cutting with a jet.
                                                                 2. Provide energy to the drill motor.
           Coatings are applied to provide a corrosion barrier and an  3. Lubricate the cutting head.
         abrasion barrier. Directional crossings generally encounter  4. Transport drill cuttings to the surface.
         varying materials and often can be exposed to extra abrasion  5. Stabilize the hole against collapse.
         during the pullback. An outer abrasion-resistant overcoat is  6. Guard against loss of slurry into surrounding formations.
         often warranted. To facilitate the pullback of the pipeline the
         coating should bond well to the pipe to resist soil stresses and  Slurry Composition—The slurries most commonly used
         have a smooth, hard surface to reduce friction and maintain  are bentonite based. Bentonite is a naturally occurring
         the corrosion barrier. As in any pipeline construction, the rec-  Wyoming clay known for its hydrophilic characteristics. Often
         ommended external coating system should be compatible  polymer extenders are also added to enhance certain charac-
         with any specifications for the field joint coating or any inter-  teristics. Material Safety Data Sheets (MSDS) are readily
         nal coating.                                          available from suppliers and can be presented to regula-
           The recommended pipe coating is mill applied fusion  tory/disposal authorities.
         bonded epoxy (FBE). The recommended minimum thickness   Containment—The slurry is pumped downhole and cir-
         is 20 mils.                                           culates back to the surface and collected in “return pits.”
   88   89   90   91   92   93   94   95   96   97   98