Risk Anaiysis applied to Subsea Pipeline Engineering                  279


                              Acceptance Crinria


                               Identification of
                               initiating events

                                 analysis

                               Cause analysis
                                (qualitative)


                                 analysis

                              Consequence  analysis
                                 (refined)





                                  Is risk
                                acceptable?

                                Acceptable
                               Desippmrocedure

        Figure 16.1 Risk Analysis Methodology.
        This chapter will outline the various techniques that are available to fulfil the requirements of
        the risk analysis stages.


        16.2  Acceptance Criteria

        16.2.1  General
        The  acceptance  criteria  are  distinctive,  normative  formulations  against  which  the  risk
        estimation  can  be  compared.  Most  regulatory  bodies  give  acceptance  criteria  either
        qualitatively or quantitatively. The NPD regulation states the following:


           In order to avoid or withstand accidental events, the operator shall define safety objectives
           to manage the activities.
           The operator shall define acceptance criteria before risk analysis is carried out.
           Risk analysis shall be carried out in order to identify the accidental events that may occur
           in  the  activities  and  the  consequences  of  such  accidental  events  for  people,  for  the
           environment and for assets and financial interest.