Page 324 - Pipelines and Risers
P. 324

Risk Analysis applied to Subsea Pipeline Engineering                 297


         The assumptions made with respect to the relative frequency of  holes of  different sizes are
         shown in Table 16.6.

         Table 16.6 Calculated Trawl Impact Frequencies.
                         Trawl Impact Frequency   Total Area   Pipeline
                                   x
                            A ~ C Y ~km)          2.63        0.42

         Risk Estimation
         The expected number of  3d  party fatalities per year  is 9.75~10~ the various scenarios
                                                              for
         considered. In view of the conservative nature of the calculations undertaken it is considered
         that the societal risks associated with the pipeline are acceptable.

         16.8.5  Environmental Risk
         No risk is posed since the material being transported is dry gas.

         16.8.6  Risk of Material Loss
         Initiating Incidents
         All  incidents considered as initiating in  the assessment of  individual and societal risks are
         considered to be initiating for the purposes of  determining the risks of material loss posed by
         the pipeline.


         In  addition  any  incidents  occurring during  construction  and  installation  and  having  the
         potential to result in damage to and/or delay in the construction of the pipeline are considered
         to be initiating with respect to Risks of Material Loss.

         Consequence Analysis
         Both repair cost and lost production cost have been assumed to be linearly related to the time
         taken for repair. Material costs for repairs have been neglected. Costs assumed are as follows:
            lost production 20 MNOK per day
            cost of repair spread 1 MNOK per day
            cost per fatality 100 MNOK

         Time required for the repair of  small or medium damage is  assumed to be  16 days (clamp
         repair), time required for repair of  large damage (new spoolpiece installed using mechanical
         connectors) is assumed to be 30 days. 3 days vessel mobilization has been assumed in each
         case.
         The costs (based on the above assumptions) incurred as the result of different sizes of damage
         are shown in Table 16.7. A discount factor of  7% is used to determine Net Present Values
         (1998 NOK) of future costs.

         The frequencies  of incidents resulting in loss of containment are summarized in Table 16.8.
   319   320   321   322   323   324   325   326   327   328   329