Page 193 - Plant design and economics for chemical engineers
P. 193

COST  ESTIMATION  167
                     j
    TABLE 4
                      of fixed-capital investment values for direct and indirect
                      ltipurpose plants or large additions to existing facilities

    Component                                                     Range, %
                   J               Direct costs
    Purchased  equipmen                                           15-40
    Purchasedequipmen installation                                 6-14
    Instrumentation  an controls  (installed)                      2-8
                  d
    Piping  (installed)                                            3-20
    Electrical  (installed                                         2-10
    Buildings  (includin  $  services) ,  !j.,  1                  3-18
                                                                   2-5
                                                                   8-20
                                                                   1-2
                                   Indirect  costs
    Engineering and su rvision                                     4-21
    Construction  expense                                          4-16
    Contractor’s  fee                                              2-6
    Contingency                                                    5-15
        Total  fixed-capital  investment







         Table 4 summarizes this typical variation in component costs as percent-
     ages of fixed-capital investment for multiprocess grass-roots plants or large
    battery-limit additions. A grass-roots plant is defined as a complete plant erected
     on a new site. Investment includes all costs of land, site development, battery-
     limit facilities, and auxiliary facilities. A geographical boundary defining the
     coverage of a specific project is a battery limit. Usually this encompasses the
     manufacturing area of a proposed plant or addition, including all process
     equipment but excluding provision of storage, utilities, administrative buildings,
     or auxiliary facilities unless so specified. Normally this excludes site preparation
     and therefore, may be applied to the extension of an existing plant.



         Example 1  Estimation of fixed-capital investment using ranges of process-plant
         component costs.  Make a study estimate of the fixed-capital investment for a
         process plant if the purchased-equipment cost is $100,000. Use the ranges of
         process-plant component cost outlined in Table 4 for a process plant handling both
         solids and fluids with a high degree of automatic controls and essentially outdoor
         operation.
   188   189   190   191   192   193   194   195   196   197   198