Methods for Correction of Power-Quality Problems 125
Pure
Leakage
path
Leakage
paths
Gaps
(a) (b)
Leakage path
Leakage
paths
(c) (d)
Figure 8.16 Leakage-reactance transformer core construction:
(a) bar shunt; (b) X core; (c) single leakage core; and (d) double leak-
age core [8.14].
such as computers, these centers require power for supporting func-
tions like air conditioning, lighting, heat exchanging, living facilities,
and maintenance. The support is usually provided by E/G sets or alter-
nate utility feeders. The centers must also be designed so equipment
Normal utility source
Engine-generator
G
Main
CB
Main bus
Non-emerg. Emerg. Gen.
CB CB CB
Transfer
To non-emergency
load switch
To emergency load
Figure 8.17 A standby system with engine generator and transfer